I-5 - NE 175th St. to NE 205th St. - NB Auxiliary Lanes - Complete June 2006

Quarterly Project Report Update for Quarter Ending December 2003

Project Title & Location
I-5/ NE 175th St to NE 205th St - Shoreline

Project Description
This project will widen NB I-5 to provide an auxiliary lane between NB on ramp at NE 175th St to NB off ramp at NE 205th St. Existing 11 foot general purpose (GP) lanes will be re-striped to 12 feet. Widening the NB on ramp at NE 175th St will provide extra GP storage at this metered location. The purpose is to improve operations and safety on I-5 by adding a NB auxiliary lane for merging and exiting traffic.

Contractor/Consultant
Project not yet advertised

Recent Progress

Project recently funded for design completion and construction with the nickel gas tax increase.  Design is continuing to bring the project to construction by October 2004.  An open house for this project was held in December with no major concerns voiced.

Design Construction Impacts
A noise wall on the west side was added to the design phase (changes must be made to accommodate).  Funding from non nickel sources has been secured for the added wall.

Environmental Impacts / Compliance

None foreseen at this time.

Impacts to Traffic
The project will support efficient operation of the general purpose and HOV lanes by controlling/directing traffic demands.  Additional roadway capacity should ease congestion on this heavily traveled route.  Traffic impacts during construction are being evaluated.  On I-5, we expect lane shifts, rolling slowdowns and lane closures.

Project Milestones Scheduled Attained Milestone Outlook
Start Project (nickel portion) May 04 May 04
Environmental Document May 02 Done
Design documentation Sep 02 Done
Environmental Permits Aug 04
Contract AD Oct 04 On schedule.  No issues affect the Ad date at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.2 21.4%
Right-of-Way
Construction $8.1 78.6%
Funded Project Costs $10.3 100.0%

Nickel funds included in above costs

$7.4 71.8%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects