I-5 - Mellen Street to Grand Mound

Quarterly Project Report Update for Quarter Ending June 2009

Project Title & Location
I-5 - Mellen Street to Grand Mound

 

Project Description
This project will widen sections of I-5 between Mellen Street in Lewis County and the Grand Mound interchange in Thurston County to increase traffic flow and safety. The project will be constructed in two stages - Stage 1: Blakeslee Junction to Grand Mound, Stage 2: Mellen Street to Blakeslee Junction.

Contractor/Consultant
David Evans and Associates, Inc. is performing a portion of the environmental reports for Stage 2.

Recent Progress
Stage 1:  Environmental DCE is complete for Blakeslee to Grand Mound. Environmental permits have been received.  The project team is completing the 100% PS&E package for review. Right of way acquisition is taking place.

Stage 2:  The project team is advancing preliminary design and environmental documentation.   

Design Construction Impacts
Stage 1:  Construction is currently scheduled for 2010. Close coordination of construction staging is on-going with Olympic Region's Grand Mound to Maytown project.

Stage 2:  Construction is currently scheduled for 2012.  Anticipated construction impacts will be assessed as the design phase is advanced.  Constructability is a major element in the design of this complex portion of I-5.

Environmental Impacts / Compliance
Stage 1:  Stormwater treatment for flow control will require off-site mitigation and right-of-way acquisition.
Stage 2:  Potential environmental impacts are being evaluated as part of the environmental documentation process.

Impacts to Traffic
Stage 1 & 2:  The design team will generate effective staging plans to minimize construction impacts to the traveling public.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering December 2005 December 2005
Environmental Documentation Complete September 2008 February 2008
Right of Way Complete February 2010 On schedule for October 2009
Advertisement February 2010
Operationally Complete December 2014
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $23.5 12.5%
Right-of-Way $16.0 9.2%
Construction $174.8 78.3%
Funded Project Costs $196.6 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$196.6 100%

  For more information, go to www.wsdot.wa.gov/projects

Colin Newell, WSDOT Area Engineer, at (360) 740-8600, or e-mail: swChehalis@wsdot.wa.gov.