I-5 - Mellen Street to Grand Mound

Quarterly Project Report Update for Quarter Ending December 2008

Project Title & Location
I-5 - Mellen Street to Grand Mound

 

Project Description
This project will widen sections of I-5 between Mellen Street in Lewis County and the Grand Mound interchange in Thurston County to increase traffic flow and safety. The project will be constructed in two stages - Stage 1: Blakeslee Junction to Grand Mound, Stage 2: Mellen Street to Blakeslee Junction.

Contractor/Consultant
David Evans and Associates, Inc. is performing 90% design for Stage 1 and a portion of the environmental reports for Stage 2.

Recent Progress
Stage 1:  Environmental Discipline Reports and DCE are complete for Blakeslee to Grand Mound. The project team is working on 90% design review. Right of way acquisition is taking place. Environmental permit applications have been submitted and permits are pending.

Stage 2:   The design team is moving forward with making the change to a collector distributor (CD) system design between the Harrison Ave and Mellen St. Interchanges.  Additionally, the CD design option was presented during an October 2nd, 2008 Open House.

Design Construction Impacts
Stage 1:  Construction is currently scheduled for 2010. Anticipated construction impacts will be assessed as the design phase is advanced. Close coordination of construction staging is on going with Olympic Region's Grand Mound to Maytown project.

Stage 2:  Construction is currently scheduled for 2012.  Anticipated construction impacts will be assessed as the design phase is advanced.  Constructability is a major element in the design of this complex portion of I-5.

Environmental Impacts / Compliance
Stage 1:  Stormwater treatment for flow control will require off-site mitigation and right-of-way acquisition.
Stage 2:  Potential environment impacts are being evaluated as part of the environmental documentation process.

Impacts to Traffic
Stage 1 & 2:  The design team will generate effective staging plans to minimize construction impacts to the traveling public.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering December 2005 December 2005
Environmental Documentation Complete September 2008 February 2008
Right of Way Complete March 2009
Advertisement April 2009 PCRF submitted to revise Advertisement date to February 2010
Operationally Complete December 2014
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $24.6 12.5%
Right-of-Way $18.0 9.2%
Construction $154.0 78.3%
Funded Project Costs $196.6 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$196.6 100%

  For more information, go to www.wsdot.wa.gov/projects

Colin Newell, WSDOT Area Engineer, at (360) 740-8600, or e-mail: swChehalis@wsdot.wa.gov.