I-5 - NB MLK Jr Way to NE Ravenna Br - Pavement Repair & More - Project map

his pavement repair project is located along nearly 13 miles of northbound I-5 from Martin Luther King Junior Way South/SR 900 to Northeast Ravenna Boulevard in Seattle

This pavement repair project is located along nearly 13 miles of northbound I-5 from Martin Luther King Junior Way South/SR 900 to Northeast Ravenna Boulevard in Seattle.

Work schedule:
Work on this project is taking place during overnight lane reductions and several scheduled weekend-long lane or full closures:

  • April 20-23: Two lanes open (COMPLETED)
  • May 11-14: Two lanes open (COMPLETED)
  • May 18-21: Two lanes open (COMPLETED)
  • June 1-4: Full northbound I-5 closure (COMPLETED)
  • July 13-16: Full northbound I-5 closure (COMPLETED)
  • Aug. 10-13: Two lanes open (COMPLETED)
  • Sept.14-17: Two lanes open