I-5 - NB MLK Jr Way to NE Ravenna Br - Pavement Repair & More


A small map of the pavement repair project along nearly 13 miles of northbound I-5 from Martin Luther King Junior Way South/SR 900 to Northeast Ravenna Boulevard in Seattle. View larger project map

A small picture of several cracked and patched concrete panels and deteriorated expansion joints on nothbound I-5 through Seattle.
There are numerous cracked and patched concrete panels and failing bridge expansion joints on northbound I-5 through Seattle.

Status

March 2017

  • This project was advertised for competitive bidding in December 2016.
  • Construction is scheduled to begin in late 2017.
  • Sign up to receive email updates about this project and other King County topics.

Overview 
Contractor crews will replace 37 expansion joints and hundreds of concrete panels on nearly 13 miles of northbound Interstate 5 from Martin Luther King Junior Way South/State Route 900 to Northeast Ravenna Boulevard through Seattle. The project also includes roadway grinding, repaving and safety barrier improvements. For specifics, see the project details page.

This is substantial weather-sensitive highway work that will require multiple nighttime lane closures, along with weekend-long lane reductions during the busy summer travel months. The project schedule must be carefully coordinated with nearby construction projects, the City of Seattle and transit agencies.

Why is WSDOT repairing this section of northbound I-5?
Approximately 236,000 vehicles use this section of northbound I-5 each day. The interstate was built in the 1960s. The concrete pavement was only intended to last 25 years, but has now doubled its lifespan.

In addition to its age, the increasing number of cars and heavy trucks on the road, along with freeze/thaw cycles, have contributed to the deterioration of the highway. Drivers can notice this in the tell-tale "thump, thump, thump" of their vehicle's wheels. That's the sign of a broken concrete panel that is rocking back and forth, and beyond its lifespan.

What should drivers expect?
To successfully complete the work, the following northbound I-5 traffic control is required:

  • Multiple weekend-long lane reductions and associated ramp closures.
  • Overnight lane and ramp closures throughout the duration of the project.
  • Generally, no closures will be allowed on Friday nights, except during the weekend lane reductions.

The End Result
This preservation and improvement work will extend the useful life of the interstate for years to come, creating safer and improved driving conditions for the thousands of travelers who use it each day. This project is part of a years-long effort to preserve I-5 through King County.

Project Benefits

  • Preservation: Replacing broken concrete panels, repaving, and grinding the roadway improves the driving surface and extends the life of I-5. Replacing bridge expansion joints ensures the highway will remain safe and operational.
  • Safety: Improving the highway surface eliminates and helps prevent future potholes, cracks and wheel ruts, making for a smoother ride for drivers. Replacing expansion joints reduces the chances that an aging expansion joint could become dislodged or fail, creating a hazard to drivers and forcing an emergency closure of the bridge.
  • Economic: Replacing broken concrete panels, repaving and replacing bridge expansion joints reduces the need for emergency repairs, which are costly to taxpayers and can cause additional congestion during peak commute hours.

What is the project timeline?

  • December 2016: Project was advertised for competitive bidding.
  • Late 2017: Construction is scheduled to begin.
  • Late 2019: Construction is scheduled to be complete.

Financial Information

Financial Data for PIN 100512T, 100515B, 100515C, 100516E, 100516G, 100519B, 100522C
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $12,242
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $24,004
CWA $0
Total $36,245

Project signage will reflect the cost of construction engineering, project bid award and sales tax.