Skip Top Navigation

I-5 James to Olive Pavement Rehab: More Facts

Traffic data

Average number of vehicles using southbound I-5 at Mercer Street

on a weekday
  122,000
on a Saturday
  102,000
on a Sunday
  94,000
on a weekday between
7 a.m.and 8 a.m.
(peak hour volume)
  10,000
on a Saturday between
noon and 1 p.m.
(peak hour volume)
  6,800
on a Sunday between
noon and 1 p.m.
(peak hour volume)
  6,600

Hourly vehicle capacity

of one freeway lane
  1,500
of southbound I-5 through downtown
  7,500 (4 mainline + 1 express lane)
 
of southbound I-5 during our
June 24-27
construction weekend
  3,000 (1 mainline + 1 express)
of southbound I-5 during our
July 15 - 18
construction weekend
  4,500 (2 mainline + 1 express)

Average number of vehicles using northbound I-5 at Mercer Street

on a weekday
  100,000
on a Saturday
  91,000
on a Sunday
  83,000
on a weekday between
4 p.m.and 5 p.m.
(peak hour volume)
  6,500
on a Saturday between
11 a.m.and noon
(peak hour volume)
  6,100
on a Sunday between
noon and 1 p.m.
(peak hour volume)
  5,800
Lane closures

Southbound I-5

Total number of lanes through
downtown Seattle
5 (including express lane, which will be southbound during construction weekends)
Lanes closed during first weekend of
construction (April 22-25)
2 of 5
Lanes closed during second weekend
of construction (June 17-20)
  4 of 5
Lanes closed during
third weekend
of construction (June 24-27)
  4 of 5
Lanes closed during
fourth weekend
of construction (July 15-18)
  3 of 5
Ramps closed during weekend 1 (April 22-25)
  2
Ramps closed during weekend 2 (June 17-20)
  3
Ramps closed during weekend 3 (June 24-27)
  5
Ramps closed during weekend 4 (July 15-18)
7

Northbound I-5

Total number of lanes through
downtown Seattle
  4 (including express lane, which will be southbound only during construction weekends)
Lanes closed during
construction
  0
Ramps closed during
construction
  0
Miscellaneous
Number of barrels required to close lanes between
Union and Dearborn streets during this weekend (July 15-18)
  375
Number of signs needed to close lanes
this weekend (July 15-18)
  30
Number of signs needed for Howell Street on-ramp detours
75
Public Outreach
Construction information fliers delivered to nearby residences and business
  36,000+
Construction and noise information fliers delivered to residences and businesses within 500 feet of the project
  750
Driver Information
Number of permanent electronic freeway signs we may use to provide driver information
14
Number of Highway Advisory Radio transmitters we may use to broadcast driver and project information
  8
Materials
Amount of concrete that crews will pour during this project
  5,100 cubic yards or 700 truckloads
Amount of asphalt that crews will remove
  6,300 cubic yards or 350 truckloads
Amount of asphalt crews will place under the new concrete
  2,400 cubic yards or 80 truckloads
Jobs
Number of construction contractors working on the project
  10 (1 prime + 9 subs)
Number of workers employed by these contractors and suppliers during the project
  100 to 200
Number working at any one time during height of weekend closures
  50 to 75
Financial
Projected total cost for design and construction
  $5.1 million
Dollar amount of contractor Merlino Construction’s construction bid:
  $3.9 million

How far could traffic back up on southbound I-5 (worst case scenerio)?
With two lanes closed
(July 15-18)

9 to 12 miles (as far as the Snohomish County line)
How far could traffic back up on northbound I-5 (worst case scenerio)?
With express lanes running southbound all weekend
  5 miles (to the north end of Boeing Field)