Design Construction Impacts
Looking for the opportunity to advance the construction start date. This requires approval to advance R/W and construction funds. It is possible to advertise this project by July 2005 using Design/Build and March 2006 using Design/Bid/Build (traditional) construction methods. Both construction methods could open the HOV lanes before the 2010 Winter Olympics.
Worked to establish a joint storm water treatment facility with the City of Everett along the bank of the Snohomish River. The major benefit of this location is eliminating the need to purchase private homes for the treatment of storm water. Received approval from the Department of Ecology in December of 2003.
Developing plans to improve the drainage system on the Lowell hillside. This hillside has a lot of water seeping out of it and several drain pipes have been installed over the decades to collect this water. The existing drainage system needs is in need of repair. A recent landslide, which was the result of a pipe breaking, confirms the need to update this drainage system.
|