Recent Progress
- FHWA approved and signed the project's environmental documentation (finding of no significant impact - FONSI) on November 10, 2004.
- FHWA approved the Access Point Decision Report (APDR) on November 18, 2004.
- Request for Proposals (RFP) advertisement was accelerated to December 1, 2004 to give Design-Build teams an entire 2005 construction season to work. If the contractor begins construction as early as May 2005 the new lanes could be open to drivers by Fall 2008 or as early as Fall 2007. This will require the advancement of $4.0 Million in construction funds in the 03-05 Biennium.
- Four pre-qualified design-build teams were short-listed on November 12, 2004. These teams will have the opportunity to submit proposals and a bid for design and construction work to build the project. The Request for Proposals (RFP) was published on Dec. 1, 2004. The winning proposal is expected to be awarded by April 2005.
|