I-5 - Grand Mound to Maytown Stage One - Add Lanes

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
I-5/Grand Mound to Maytown Stage One -Add Lanes (Thurston County)

Project Description
This project widens I-5 from Grand Mound (US 12 West I/C) to Maytown by adding one lane in each direction. The work includes flattening an existing freeway curve, improving the Grand Mound and Maytown interchange ramps, and improving Rest Area ramps. There are currently four lanes. There will be six lanes when this project is completed.

Contractor/Consultant
The project was awarded 3-17-2008 to Scarsella Bros., Inc.

Recent Progress
Project has been awarded.

Design Construction Impacts
Execution pending.

Environmental Impacts / Compliance

This project will have minor wetland impacts.  The project will use wetland bank credits that have been established in the corridor to mitigate for project impacts.

The Contractor must comply with imposed restrictions outlined in the contract provisions.  An Environmental Compliance Plan has been prepared.

Impacts to Traffic
During construction, nighttime lane closures and daytime width reductions will be necessary.  Bridge replacement will require long term narrowing of lanes and traffic shifts.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering  May 11, 1998   May 11, 1998
Environmental Documentation Complete         August 2, 2006  August 16, 2007
Right of Way Acquisition Complete September 18, 2007   November 26, 2007
Advertisement Date October 1, 2007   December 10, 2007
Operationally Complete December 9, 2009   Likely more than a two season project. Operational completion date now estimated at June 16, 2010.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 6.05      6.9%
Right-of-Way $  2.50     2.8%
Construction $79.43   90.3%
Funded Project Costs $87.99 100.0%

Nickel funds included in above costs

$84.52   96.1%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects