I-5 - Grand Mound to Maytown Stage One - Add Lanes

Quarterly Project Report Update for Quarter Ending March 2007

Project Title & Location
I-5, Grand Mound to Maytown Widening - Thurston County

Project Description
This project widens I-5 from Grand Mound (US 12 West I/C) to Maytown by adding one lane in each direction. The work includes flattening an existing freeway curve, improving the Grand Mound and Maytown interchange ramps, and improving Rest Area ramps. There are currently four lanes. There will be six lanes when this project is completed.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The project office is currently developing contract plans. A 60% design constructability review has been conducted. Environmental documentation and permit applications are essentially complete. Right of way acquisition is ongoing for one parcel.

The Legislature is considering ways to fund Stage 2; the improvements to the Grand Mound Interchange.

Design Construction Impacts
To facilitate construction staging, a temporary bridge will be constructed adjacent to Southbound I-5, over Prairie Creek. This will be done to minimize impact to the traveling public and mitigate construction challenges.

Environmental Impacts / Compliance

This project will have minor wetland impacts.  The project will use wetland bank credits that have been established in the cooridor to mitigate for project impacts.

The design team is developing plans to replace one fish barrier culvert with one that will allow fish passage to upstream habitat.

Impacts to Traffic
During construction, nighttime lane closures and daytime width reductions will be necessary.  Bridge replacement will require long term narrowing of lanes and traffic shifts.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Documentation Complete          July 2006   January 2007 The Environmental Documentation phase for this project is complete.  Work to obtain the necessary permits has begun.
Access Point Decision Report Complete          July 2006   May 2006 The APDR for modifications to the Grand Mound Interchange has been approved by FHWA.
Right of Way Acquisition Complete October 2007   Two parels are needed for stormwater treatment ponds.
Advertisement Date October 2007   No issues at this time.
New lanes open to traffic December 2009   No issues at this time. 
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $  5.90     7.5%
Right-of-Way $  3.04     3.8%
Construction $70.25   88.7%
Funded Project Costs $79.19 100.0%

Nickel funds included in above costs

$73.22   92.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton, Project Engineer, (360) 570-6606