I-5 - Grand Mound to Maytown Stage One - Add Lanes

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
I-5/Grand Mound to Maytown Stage One -Add Lanes (Thurston County)

Project Description
This project widens I-5 from Grand Mound (US 12 West I/C) to Maytown by adding one lane in each direction. The work includes flattening an existing freeway curve, improving the Grand Mound and Maytown interchange ramps, and improving Rest Area ramps. There are currently four lanes. There will be six lanes when this project is completed.

Contractor/Consultant
Project has been advertised; not yet awarded pending receipt of bids.

Recent Progress
Plans, Specifications, and Estimates are complete. All environmental permits are in hand (notwithstanding Ecology approval of SSDP/SCUP).   ROW negotiations are complete and headed for closing.  Preliminary work for utility relocations is progressing satisfactorily. Project Development Approval has been granted and the design record is substantially complete.

Design Construction Impacts
To facilitate construction staging, a temporary bridge will be constructed adjacent to Southbound I-5, over Prairie Creek. This will be done to minimize impact to the traveling public and mitigate construction challenges.

Environmental Impacts / Compliance

This project will have minor wetland impacts.  The project will use wetland bank credits that have been established in the corridor to mitigate for project impacts.

The fish passage barrier culvert replacement has been eliminated in favor of upgrading with a substantially less costly wall. Following a site inspection, a determination was made that the existing culvert remains serviceable and in excellent condition.

Impacts to Traffic
During construction, nighttime lane closures and daytime width reductions will be necessary.  Bridge replacement will require long term narrowing of lanes and traffic shifts.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering  May 11, 1998   May 11, 1998
Environmental Documentation Complete         August 2, 2006  August 16, 2007 Environmental permitting is complete.
Right of Way Acquisition Complete September 18, 2007   One parcel is needed for stormwater treatment ponds.  Negotiated settlement reached and in closing.  R/W certification is imminent.
Advertisement Date October 1, 2007   December 10, 2007 On Ad December 10, 2007.
Operationally Complete December 9, 2009   Likely more than a two season project. Operational completion date now estimated at April 15, 2010.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 6.05      6.9%
Right-of-Way $  2.50     2.8%
Construction $79.43   90.3%
Funded Project Costs $87.99 100.0%

Nickel funds included in above costs

$84.52   96.1%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton, Project Engineer, (360) 570-6606