Recent Progress
The local jurisdictions are moving forward with the idea to establish a diking district for the continual operation, maintenance, and remaining capital cost of the project. Earlier this year the recommendation to change the project from the “Lewis County Flood Control Project” to the “Interstate 5 protection Project” was sent to the legislators for their approval.
The new project is waiting for the Airport Road extension to be modeled, with the Lewis County arterial model, to determine whether it needs to be 2 or 4- lane. Once this determination is made a consultant will be hired to complete the plans, specification and estimate for constructing a levee along Airport Road as well as raising the existing levee around the airport.
|