I-5 - Chehalis River Basin Flood Reduction

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
I-5/Chehalis River Flood Control

Project Description
This project is a partnership with Lewis County to reduce flood impacts to I-5 and the Chehalis River Basin.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

Lewis County and the U. S. Army corps of Engineers (USCOE) had been expected to partner with WSDOT in funding this project.  In September 2004, the USCOE advised WSDOT that Congress had not authorized funding for this project.  As a result WSDOT defered $500,000 of perliminary engineering funds from the 03-05 biennium to the 05-07 biennium.  Since then Lewis County has had their consultant sign a addendum which has PIE continuing to analysis the Skookumchuck River Dam, and writting a report detailing the work accomplished on the final design plans and specifications.  The addendum also has PIE evaluating the levee locations through out the basin as well as determining what changes removing the Mellon Street Bridge would have on 100-year flood elevation in the Airport Road Levee vicinity.

Design Construction Impacts

The USACE has indicated that, as a stand-alone project, the proposed dam modifications project would likely have no benefits for I-5, either in cost savings or reduced traffic delay.  Further hydraulic modeling has been requested.  Without direct benefits to the highway system WSDOT will not be able to contribute any "Nickel" gas tax money to this portion of the flood control project.

Environmental Impacts / Compliance

The Chiefs report was signed on Sept. 27, 2004

The Lewis County / PIE River Mile 66 Habitat Enhancement Project  has encountered significant resistance from the Chehalis Tribe and as such the RM 66 project may be cancelled. The USACE has stated they oppose this component and they did not include it in the GRR or FEIS.

Impacts to Traffic

None at this time.

Project Milestones Scheduled Attained Milestone Outlook
Design Start December 2003 December 2003 Began on time.
Record of Decision March 2006  
Right of Way Complete December 2006  
Ad Date January 2007

 

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $4.0 13.3%
Right-of-Way $6.0 20%
Construction $20.0 66.7%
Funded Project Costs $30.0 100%

Nickel funds included in above costs

$30.0 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Rich Hensley, WSDOT Area Engineer, at (360) 740-8600, or e-mail: henslerg@wsdot.wa.gov.