Recent Progress
The US Army Corps of Engineers has published the final General Reevaluation Report (GRR) and the final Environmental Impact Statement (EIS) for this project.
WSDOT reimbursed Lewis County for expenses generated over the last two years and now has an agreement in place to reimburse the County for current expenditures from their consultant, Pacific International Engineering (PIE). This agreement also establishes the roles and responsibilities between the agencies for this project.
The Dam modifications provide no direct benefit to the Interstate as a stand-alone project. Therefore, WSDOT may not be able to participate financially in this major aspect of the project.
|