I-5 - Chehalis River Basin Flood Reduction

Quarterly Project Report Update for Quarter Ending December 2004

Project Title & Location
I-5/Chehalis River Flood Control

Project Description
This project is a partnership with Lewis County to reduce flood impacts to I-5 and the Chehalis River Basin by raising and widening Airport Way, a frontage road on the west side of I-5.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

The U.S. Army Corps of Engineers' (USACE) Chief's Report, which defines the project's scope, schedule and budget, has been signed and will be submitted to Congress.  At this time, the USACE does not have funding appropriated for construction or engineering review.  The USACE, Lewis County and WSDOT are preparing agreements to allow WSDOT to fund critical USACE work in order to keep the project moving forward.

 

Design Construction Impacts

The USACE has indicated that, as a stand-alone project, the proposed dam modifications project would likely have no benefits for I-5, either in cost savings or reduced traffic delay.  Further hydraulic modeling has been requested.  Without direct benefits to the highway system WSDOT will not be able to contribute any "Nickel" gas tax money to this portion of the flood control project.

Environmental Impacts / Compliance

Next critical task is the issuance of the USACE Chief’s Report to Congress.  This includes the dam modification and levees. 

Lewis County is pushing the RM 66 Habitat Enhancement (also known as Flood Way Bypass) as a major component of the project.  The USACE has stated they oppose this component and they did not include it in the GRR or FEIS.

Impacts to Traffic

None at this time.

Project Milestones Scheduled Attained Milestone Outlook
Design Start December 2003 December 2003 Began on time.
Record of Decision March 2006  
Right of Way Complete December 2006  
Ad Date January 2007

 

Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $4.0 13.3%
Right-of-Way $6.0 20%
Construction $20.0 66.7%
Funded Project Costs $30.0 100%

Nickel funds included in above costs

$30.0 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Rich Hensley, WSDOT Area Engineer, at (360) 748-2353 or e-mail: hensler@wsdot.wa.gov