I-5 - Bakerview Road to Nooksack River Bridge

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location
I-5, Bakerview Road to the Nooksack River Bridge, concrete pavement reconstruction, Bellingham to Ferndale

Project Description
This project will repair and replace segments of southbound Interstate 5 from Ferndale to Bellingham, between Bakerview Road and the Nooksack River Bridge.

Contractor/Consultant
Project has not been advertised or awarded.

Recent Progress

The project design office has recommended changing the type of safety work on this project. The design office is currently working with program Development and Management to get their concurrence.

Design Construction Impacts

Maintenance has requested the replacement of faulty concrete panels in the vicinity of Slater Rd. I/C for both N and S bound I-5 lanes.  WSDOT materials lab. has make recommendation for appropriate fix.  Program Management will be given a cost estimate of ($215k to $250k) for this additional work for their approval.  Project limits need to be extended to accommodate the added work in the north bound lane. 

Environmental Impacts / Compliance

After flagging and mapping the wetlands it has been determined that the safety improvements included in this project will effect wetlands.

Impacts to Traffic

We are just beginning the project design.  Impacts from the design and construction are not known yet.

Project Milestones Scheduled Attained Milestone Outlook
Start Project May 04 March 04  Complete project design.  Start to develop the contract plans.
Wetland mitigation determination complete June 05 Determine if wetland mitigation is necessary.
Develop Work zone traffic control plan November 04 Develop a work zone traffic control plan for ramp improvements and pavement reconstruction.
Environmental permits acquired September 05

No issues at this time.

Contract advertised January 06 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.3 m 8.8%
Right-of-Way
Construction $3.1 m 91.2%
Funded Project Costs $3.4 m 100%

Nickel funds included in above costs

$0.7 m 20.6%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects