I-5 - Bakerview Road to Nooksack River Bridge

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
I-5, Bakerview Road to the Nooksack River Bridge, concrete pavement reconstruction, Bellingham to Ferndale

Project Description
This project will repair and replace segments of southbound Interstate 5 from Ferndale to Bellingham, between Bakerview Road and the Nooksack River Bridge.

Contractor/Consultant
The project has not been advertised or awarded.

Recent Progress

The project team submitted a request for additional funds to account for the recent rise in materials cost.  The project team also met with Maintenance on site to look over the project to determine what areas of work should be completed first if scope of project is cut back to met the current budget.  Work force needs may require needing to bring on a consultant to help deliver the project.

The project office will provide documentation to eliminate the slope flatting and ramp taper lengthening work based upon impacts to wetlands and accident history. The deletion of this work will remove the Nickel funding from this project.

Design Construction Impacts

Impacts from the design and construction are not known yet.

Environmental Impacts / Compliance
No wetland impacts are anticipated with the elimination of the slope flattening portion of this project.

Impacts to Traffic

Impacts from the design and construction are not known yet.

Project Milestones Scheduled Attained Milestone Outlook
Begin Prelim Engineering Nov. 2005   Start development of project design.
Right of Way Certified NA No right of way
Environmental Complete Dec 2006  No issues at this time.
Advertisement Jan 2007

No issues at this time.

Open to Traffic Fall 2007 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.4 m 11.4%
Right-of-Way
Construction $3.1 m 88.6%
Funded Project Costs $3.5 m 100%

Nickel funds included in above costs

$0.7 m 20.0%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

David Crisman, WSDOT Project Engineer @ (360)428-1593 or E-mail: crismad@wsdot.wa.gov