I-5 - Bakerview Road to Nooksack River Bridge

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
I-5, Bakerview Road to the Nooksack River Bridge, concrete pavement reconstruction, Bellingham to Ferndale

Project Description
This project will repair and replace segments of southbound Interstate 5 from Ferndale to Bellingham, between Bakerview Road and the Nooksack River Bridge.

Contractor/Consultant
The project has not been advertised or awarded.

Recent Progress
Project has been deyaled for two years to help balance the state wide paving program. The project design will resume November 2007.

Design Construction Impacts
Impacts from the design and construction are not known yet.

Environmental Impacts / Compliance
Impacts from the design and construction are not known yet.

Impacts to Traffic
Impacts from the design and construction are not known yet.

Project Milestones Scheduled Attained Milestone Outlook
Begin Prelim Engineering Nov 2007   Start development of project design.
Right of Way Certified NA No right of way
Environmental Complete Sept. 2008  No issues at this time.
Advertisement Oct. 2008 No issues at this time.
Open to Traffic Fall 2009 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.3 m 10.3%
Right-of-Way
Construction $2.6 m 89.7%
Funded Project Costs $2.9 m 100%

Nickel funds included in above costs

   

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

David Crisman, WSDOT Project Engineer @ (360)428-1593 or E-mail: crismad@wsdot.wa.gov

 

Project Cost Summary reflects the March 2006 Approved Legislative Supplemental Budget