Project Title & Location
I-5 / 5th Ave NE to NE 92nd Street Noise Wall Project, Seattle
|
Project Description
WSDOT has completed major construction work on three noise walls in the Licton Springs and north Green Lake Neighborhoods. Final landscaping will be completed in Fall 2009. WSDOT is also constructing one noise wall along I-5 in the Maple Leaf neighborhood. WSDOT is working with Sound Transit to coordinate construction with the North Link light rail project proposed for the same area. Construction is scheduled to begin Fall 2009.
|
|
Contractor/Consultant
Design - HDR Engineering, Perteet Engineering Construction - Wilder Construction Company
|
|
Recent Progress
Preliminary engineering work for Stage 1 is complete. The project was awarded to Wilder Construction Company in early April. The design team is hosting two construction information session on June 5 and June 7 and continues to coordinate with neighbors in the form of e-mail, telephone, and on-site visits to answer questions about the project.
The team met the 30% submittal date for Stage 2 design work on March 31, 2008 and will involve the community in a polling process to determine support for a wall in this location this summer. The team will continue to monitor Sound Transit’s plans for the North Link light rail project that is proposed to be built in the same area.
For a full description of the project, please visit the project web page: http://www.wsdot.wa.gov/Projects/I5/5thAveNEtoNE92ndNoiseWall/
|
|
Design Construction Impacts
Construction of Stage 1 is expected to begin in June 2008. The work will involve temporary modifications to off-ramps and possible lane restriction on I-5 during night work.
|
|
Environmental Impacts / Compliance
The project's resultant noise reduction is beneficial to the surrounding environment and communities.
During construction the contractor will install erosion control measures to contain sediment and debris at the construction site.
Requests for noise variances for night time work have been obtained from the City of Seattle.
|
Impacts to Traffic
The work will involve temporary modifications to off-ramps and possible lane restriction on I-5 during night work.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Begin Preconstruction Engineering
|
January 2006
|
January 2006
|
|
|
Environmental Document Complete
|
December 2009
|
|
On track to complete all environmental documentation. Milestone date is for the stage 2 project.
|
|
Right of Way Certification Complete
|
March 2009
|
|
On track to complete all Right of Way Certifications. Milestone date is for the stage 2 project
|
|
Advertisement Date
|
Stage 1 - Feb. 2008 Stage 2 - April 2009
|
Stage 1 - Feb. 2008
|
On track to meet Stage 1 Ad Date as scheduled
|
|
Operationally Complete
|
September 2010
|
|
Major construction on the Stage 2 project is scheduled to be completed in the fall of 2010. Landscape maintenance will continue for another two years.
|