Project Title & Location
I-5 / 5th Ave NE to NE 92nd Street Noise Wall Project, Seattle
|
Project Description
WSDOT has completed major construction work on three noise walls in the Licton Springs and north Green Lake Neighborhoods. Final landscaping will be completed in Fall 2009. WSDOT is also constructing one noise wall along I-5 in the Maple Leaf neighborhood. WSDOT is working with Sound Transit to coordinate construction with the North Link light rail project proposed for the same area. Construction is scheduled to begin Fall 2009.
|
|
Contractor/Consultant
HDR Engineering, EnviroIssues, Parsons Brinckerhoff, David Evans & Associates, Perteet Engineering, So-Deep, Granite Construction dba Wilder Construction Company, Massana Construction, Inc.
|
|
Recent Progress
Stage 1: Crews have finished installing all of the noise wall panels, drainage trenches and access gates. Major construction completed in June 2009. Final construction of landscaping and roadside restoration will be done in Fall 2009 which will complete work on Stage 1 of the project. The WSDOT team continues to coordinate with neighbors in the form of e-mail, telephone, fliers, and on-site visits to answer questions about the project.
Stage 2: The design team completed 100 percent design for Wall 1-North, which will be constructed using a non-concrete product called Carsonite AcoustaShield. The project was advertised in June 2009 and awarded in July 2009 to Massana Construction, Inc. The team is continuing to coordinate with Sound Transit in regard to the planned North Link Light Rail line that will be constructed in the same area as the noise wall. The Construction of Wall 1-North is scheduled to begin in fall 2009. The WSDOT team will continue to coordinate with neighbors in the form of e-mail, telephone, fliers and on-site visits throughout the construction phase.
For a full description of the project, please visit the project web page.
|
|
Design Construction Impacts
Construction of Stage 1 began in June 2008. All traffic alignments have been returned to their original configurations.
|
|
Environmental Impacts / Compliance
The project's resultant noise reduction is beneficial to the surrounding environment and communities.
During construction the contractor will install erosion control measures to contain sediment and debris at the construction site.
Street use permits and noise variances for night time work have been obtained from the City of Seattle for Stage 1. Night work is not anticipated for Stage 2, but street use permits will be required.
|
Impacts to Traffic
Stage 1 traffic alignments are back to their original configurations.
Stage 2 traffic impacts will include periodic lane closures on 1st Avenue NE, parking restrictions on 1st Avenue NE and shoulder closures on northbound I-5 near Wall 1-North.
|
| Project
Milestones |
Scheduled |
Attained |
Milestone Outlook |
|
Begin Preconstruction Engineering
|
January 2006
|
January 2006
|
Complete.
|
|
Environmental Document Complete
|
January 2009
|
Complete
|
On track to complete all environmental documentation. Milestone date is for the stage 2 project.
|
|
Right of Way Certification Complete
|
March 2009
|
Complete
|
On track to complete all Right of Way Certifications. Milestone date is for the stage 2 project.
|
|
Advertisement Date
|
Stage 1 - Feb. 2008 Stage 2 - June 2009
|
Complete
|
On track to meet Stage 2 Ad Date as scheduled.
|
|
Operationally Complete
|
June 2010
|
|
Major construction on the Stage 2 project is scheduled to be completed in the fall of 2010. Landscape maintenance will continue for another two years.
|