Skip Top Navigation

Construction Photos

Wall 4 - Installed Noise Wall

View more construction progress and other images for this project on the WSDOT Flickr site.


Neighborhood side of Wall 4 near NE Longwood Place.
Neighborhood side of the installed noise wall near NE Longwood Place.

Dry Stack Stone pattern on the neighborhood side of Wall 4.
Neighbors chose the Dry Stack Stone pattern for the neighborhood side of Wall 4.

Wall 2 - Installed Noise Wall

Neighborhood side of the noise wall near NE 92nd Street. Neighbors chose the Ashlar Stone pattern.
Neighborhood side of the installed noise wall near NE 92nd Street. Neighors chose the Ashlar Stone pattern.




Highway side of the installed noise wall near NE 92nd Street. Crews are completing the finishing touches now that the panels are installed.
Highway side of the installed noise wall near NE 92nd Street. Crews are completing the finishing touches now that the panels are installed.

Wall 2 - December Noise Wall Panel Installation

Noise wall panels are delivered on large trucks to the site.
The noise wall panels are delivered on large delivery trucks to the site. A large crane lifts a panel from the truck.


The crane lifts the panel from the delivery truck and up and over existing trees to the installation site.


The crane lowers the panel to a waiting crew.

A crew steadies a noise wall panel and lowers it onto the recently constructed foundation.
A crew steadies a noise wall panel and lowers it onto the recently constructed foundation.

The panel is secured to the foundation.
The panel is secured to the foundation.
 
A crew prepares for the next panel to arrive.
A crew prepares for the next panel to arrive.

Wall 3 - July Construction

The work zone for Wall 3 between homes and the exit to N 80th Street.
The work zone for Wall 3 between homes and the exit to N 80th Street.

Construction workers use a drill to make a shaft for the noise wall foundation.
Construction workers use a drill to make a shaft for the noise wall foundation.

A crew lowers a rebar cage into a newly drilled shaft.
A crew lowers a rebar cage into a newly drilled shaft.

Concrete workers fill shafts and set the rebar cages in place.
Concrete workers fill shafts and set the rebar cages in place.

A completed concrete foundation with bolts to anchor the noise wall panels.
A completed concrete foundation with bolts to anchor the noise wall panels.