Skip Top Navigation

Construction Photos

View more construction progress and other images for this project on the WSDOT Flickr site.

Wall 1 - Construction


Crews lower the upper portion of the wall into place.


The vertical planks of the wall are installed.


The Carsonite planks are made of a composite that is strengthened with fiberglass and filled with ground-up tire rubber.

Wall 4 - Completed

Neighborhood side of Wall 4 near NE Longwood Place.
Neighborhood side of the installed noise wall near NE Longwood Place

Dry Stack Stone pattern on the neighborhood side of Wall 4.
Neighbors chose the Dry Stack Stone pattern for the neighborhood side of Wall 4.

Wall 2 - Completed

Neighborhood side of the noise wall near NE 92nd Street. Neighbors chose the Ashlar Stone pattern.
Neighborhood side of the installed noise wall near NE 92nd Street. Neighors chose the Ashlar Stone pattern.

Highway side of the installed noise wall near NE 92nd Street. Crews are completing the finishing touches now that the panels are installed.
Highway side of the installed noise wall near NE 92nd Street.

Wall 2 - Construction

Noise wall panels are delivered on large trucks to the site.
The noise wall panels are delivered on large delivery trucks to the site. A large crane lifts a panel from the truck.

A crew steadies a noise wall panel and lowers it onto the recently constructed foundation.
A crew steadies a noise wall panel and lowers it onto the foundation.

The panel is secured to the foundation.
The panel is secured to the foundation.

Wall 3 - Construction

Construction workers use a drill to make a shaft for the noise wall foundation.
Construction workers use a drill to make a shaft for the noise wall foundation.

A crew lowers a rebar cage into a newly drilled shaft.
A crew lowers a rebar cage into a newly drilled shaft.

Concrete workers fill shafts and set the rebar cages in place.
Concrete workers fill shafts and set the rebar cages in place.