Project Title & Location
I-5/Second Street Bridge - Replace Bridge - Mount Vernon
|
Project Description
This project replaces a low-clearance bridge over I-5, eliminating a through-city detour now required for over-height trucks. The new bridge eliminates the risk of over-height trucks hitting the bridge over busy I-5 and will meet seismic standards.
|
|
Contractor/Consultant
Project was awarded to Mowat Construction on June 1 for 2% over engineers estimate.
|
|
Recent Progress
Work resumed on June,10 2006 with reconstructing the slow lane shoulders of I-5 under 2nd street bridge in preparation for lane shifts. Work in August included paving of south bound lanes to bring the pavement even with the north bound lanes, removing the old cast in place barrier between north and south bound lanes and placing it with new pre-cast barrier.
|
|
Design Construction Impacts
Project complete September 26, 2006 within contract days and budget.
|
|
Environmental Impacts / Compliance
Project complete no enviromental impacts.
|
Impacts to Traffic
Project complete no impacts to traffic.
|