|
Project Title & Location
I-5/Second Street Bridge - Replace Bridge - Mount Vernon
|
Project Description
This project replaces a low-clearance bridge over I-5, eliminating a through-city detour now required for over-height trucks. The new bridge eliminates the risk of over-height trucks hitting the bridge over busy I-5 and will meet seismic standards.
|
|
Recent Progress
The project is roughly 85% complete. The Contractor has built all the 6 spans that make up the new bridge and has completed 85% of the pedestrian barrier. The west approach in the downtown area is 95% complete with final lift of paving remaining. The east approach is 80% complete with sidewalks and paving remaining. Work on reconstructing SR536 will be finished early November with sidewalks, drainage, and asphalt. Bridge scheduled to open mid October.
|
|
Environmental Impacts / Compliance
The Contractor discovered contaminated soils while installing a manhole. Test showed the soil was contaminated but not hazardous. The drainage structure has been installed and the cost associated with addressing the contaminated soils are being determined.
|
Impacts to Traffic
Traffic will be detoured through Mount Vernon at night when full directional closure of I-5 is required (Contractor has used 7 of the 23, I-5 closures allowed in the contract). Mitigation efforts include a comprehensive public awareness campaign. The next I-5 closures will occur this fall to remove the forms over I-5. The forms are being used to build the new bridge.
|