|
Project Title & Location
I-5/Second Street Bridge - Replace Bridge - Mount Vernon
|
Project Description
This project replaces a low-clearance bridge over I-5, eliminating a through-city detour now required for over-height trucks. The new bridge eliminates the risk of over-height trucks hitting the bridge over busy I-5 and will meet seismic standards.
|
|
Contractor/Consultant
Project was awarded to Mowat Construction on June 1 for 2% over engineers estimate.
|
|
Recent Progress
The Contractor has completed removing the existing 2nd St. bridge and is currently working on installing the foundation for the new bridge. The Contractor has completed 13 of the 21 shafts that make up the foundation for the new bridge.
|
|
Design Construction Impacts
The project start date was delayed to investigate a Contractor's proposed design changes to the new bridge piers next to I-5. This change reduced the number of days the bridge would be closed from 225 to 210 days, saved $110,000, and reduced traffic control on I-5. Contract work started three months later than original scheduled to give the Contractor time to redesign the bridge and give WSDOT time to review the changes. The change was accepted and the Contractor began removing the existing bridge in late October.
|
|
Environmental Impacts / Compliance
No significant impacts. Agreement with the City of Mount Vernon to treat water from new bridge.
|
Impacts to Traffic
Traffic will be detoured through Mount Vernon at night when full directional closure of I-5 is required (Contractor has used 3 of the 23, I-5 closures allowed in the contract). Mitigation efforts include a comprehensive public awareness campaign.
|