I-5 - 2nd Street Bridge Replacement - Complete September 2006

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location
I-5/Second Street Bridge - Replace Bridge - Mount Vernon

Project Description
This project replaces a low-clearance bridge over I-5, eliminating a through-city detour now required for over-height trucks. The new bridge eliminates the risk of over-height trucks hitting the bridge over busy I-5 and will meet seismic standards.

Contractor/Consultant
Mowat Construction Company was awarded the project on June 1, 04 for $9.39 million dollars.

Recent Progress

Contractor has proposed changing the foundations for piers in the I-5 roadway prism.  The new design decreases the cost of the project by $50,000 and will provide less severe lane shifts on I-5.  The plans called for lane shifts up to 12 feet and the Contractors proposal will shift the lanes up to 2 feet.  The Contractor's proposal has been accepted and is being incorporated into the contract.  The Contractor has begun removing the old bridge and is scheduled to complete this work by the first week of November.

Design Construction Impacts

The Second Street Bridge detour will be in place from October 04 through August 05. 

Environmental Impacts / Compliance
No significant impacts.  Agreement with City of Mount Vernon to treat water from new bridge.

Impacts to Traffic
Local traffic will begin using the detour for the Second Street bridge closure starting October 11 and the detour will be in place through mid August 05.  I-5 detours will be in place last week of October 04 and once again around the first week of August 05. Only one direction of traffic on I-5 will be permitted to be closed at any time. Mitigation efforts include a comprehensive public awareness campaign.

Project Milestones Scheduled Attained Milestone Outlook
Start Project August 2004 September 2004 Contractor mobilize equipment on the job site to begin work.
Bridge removal September 2004   Second Street bridge detour in place,bridge removed.
Install shafts November 2004 Install shafts for piers 1 through 7.
Bridge open to traffic August 2005

Contractor has two lanes of the new Second Street bridge open to traffic.

Contract complete September 2005 Contractor has completed all items of work.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.8 13.1%
Right-of-Way $0.3 2.6%
Construction $11.6 84.3%
Funded Project Costs $13.7 100%

Nickel funds included in above costs

$12.0 87.6%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

David Crisman, WSDOT Project Engineer @ (360)428-1593 or E-mail: crismad@wsdot.wa.gov