I-5 - 2nd Street Bridge Replacement - Complete September 2006

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
I-5/Second Street Bridge - Replace Bridge - Mount Vernon

Project Description
This project replaces a low-clearance bridge over I-5, eliminating a through-city detour now required for over-height trucks. The new bridge eliminates the risk of over-height trucks hitting the bridge over busy I-5 and will meet seismic standards.

Contractor/Consultant
Project was awarded to Mowat Construction on June 1 for 2% over engineers estimate.

Recent Progress

Tuesday October 18, 2005 we opened the new 2nd street bridge to traffic.   SR536 work completed includes first lift of asphalt, drainage, and curb and sidewalk. The remaining work on SR536 includes final lift of asphalt and striping, this work will be completed summer 2006.  The parking lots are reconstructed and ready for use. The slope on the east side of I-5 have been graded and permanent slope erosion protection installed.

Design Construction Impacts

Work to remove and replace the cast-in-place barrier and paving of southbound I-5 in the vicinity of the new bridge will begin in August. This work  will require a lane closure of northbound and southbound I-5 at night. This work will also include drainage improvements and reconstruction of the northbound I-5 right shoulder .

Environmental Impacts / Compliance

The City of Mount Vernon discovered buried fuel tank on County R/W in a parking lot that was being overlaid as part of this project. The tank was removed and environmental issues addressed. No other issues at this time.

Impacts to Traffic
Traffic will be detoured through Mount Vernon at night when full directional closure of I-5 is required (Contractor has used 11 of the 23, I-5 closures allowed in the contract).   Mitigation efforts include a comprehensive public awareness campaign. The next I-5 closures will occur this spring to remove and replace median barrier, construct new drainage, and pave south bound I-5 in the vicinity of the new bridge.

Project Milestones Scheduled Attained Milestone Outlook
PE Start Date June 2000 June 2000  Begin to develop the plans and specification.
Right of Way Certified March 2004 April 2004  Right of Way need to build the project purchased.
Environmental Complete January 2004  December 2002 Environmental permits required.
Advertisement April 2004 April 2004

Mowat Construction Company was low bidder.  Project awarded to Mowat June 1, 2004.

Open to traffic September 2005 October 2005  New bridge will be open to traffic early fall and the total project completed spring 2006.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.2 15.3%
Right-of-Way $0.2 1.4%
Construction $12.0 83.3%
Funded Project Costs $14.4 100%

Nickel funds included in above costs

$9.5 65.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

David Crisman, WSDOT Project Engineer @ (360)428-1593 or E-mail: crismad@wsdot.wa.gov