Skip Top Navigation


Keep Informed:
Sign up for Snohomish construction updates.

Sign up for other WSDOT updates.

I-5 - 124th St. Bicycle/Pedestrian Overpass Photos

Ribbon Cutting Ceremony - April 28, 2008

People cutting the ribbon
Representatives from Snohomish County, Community Transit, Snohomish County Park and Recreation, WSDOT and Snohomish County Public Works cut the ribbon!

Looking at finished trail facing I-5
The finished trail leading up to the overpass, facing I-5.

Looking at the finished trail on the other side of the bridge
The finished trail on the other side of the overpass.

People at the event
Bicyclists and community members enjoy refreshments provided by BIKES club of Snohomish County. 

Looking at bicyclists
Bicyclists at the event.

Looking at County Executive Aaron Reardon
County Executive Aaron Reardon speaks about the overpass.


WSDOT Assistant Regional Administrator for Snohomish County, Russ East, speaks at the event.

Project Engineer Marlin Lenssen
WSDOT Project Engineer Marlin Lenssen standing beside the overpass.

Looking at bikes
Bikes on the bridge.

Looking at Community Tranist Representative, Oxy Gene
Community Transit Representative, Oxy Gene, striking a pose.

Looking at bicyclists using the bridge
A pair of bicyclists put the new bridge to use.



March 2008


Looking south from the 124th Street bridge: the new retaining wall is complete and crews are working on finishing touches to landscaping.


The pedestrian trail leading up to the 124th Street bridge is paved and nearly ready for use. Crews are installing fencing and completing landscaping along the trail.

January 2008

In January, crews began building the retaining wall on the east side of I-5, which fits together like a jigsaw puzzle.


The wall, under construction, as viewed from southbound I-5.


The pedestrian trail heading north toward the overpass.

Late 2007

Crews have excavated the path for the new trail and work to build a base for the retaining wall.


Crews work to place the first piece of a new wall that will fit together like a puzzle.

Fall 2006
Crews completed the overpass on July 6, 2006
Crews finished building the overpass on July 6, 2006. 

Spring 2006
Crews setting gider over I-5 at 124th Street Southwest for new bridge.
Crews carefully setting an enormous girder over I-5 on the piers installed during the winter. Workers successfully set two girders over two nights that will form the frame of the bridge deck.

Winter 2006
Crew excavating on the side of I-5 at 124th Street Southwest for new bridge piers.
A Mowat construction crew member overseeing excavation work at the project site. In winter 2006 crews excavated and installed bridge piers on both sides of I-5 to support the new bridge structure.