Jan. 25 - At the metal girder fabrication plant in Portland, Oregon where workers are manufacturing the steel girders we'll install to form the NE 128th bridge over I-405. Jan. 25 - Installing waterline along NE 128th Street near Totem Lake Blvd.Jan. 25 - Building a retaining wall on the southbound side of I-405. We're building this wall so we can widen the freeway to the west. Jan. 24 - We've shifted northbound I-405 traffic away from the median between NE 124th and NE 132nd to provide room to build supports for the NE 128th bridge in the median. We're currently preparing the west side of the freeway to shift southbound traffic away from the median.