April 17 - We shifted southbound I-405 traffic (left side of this photo) on Wednesday, April 12. Now both northbound and southbound traffic are moved away from the median so we can build another bridge support and the HOV ramps at NE 128th. You can see the girders for the east half of the bridge in place at the upper right of this photo.

April 17 - A wide shot taken from Totem Lake Blvd. of the east half of the new NE 128th bridge. We're building walls in the median (right) to support the new HOV on- and off-ramps.

April 6 - Looking south from the east half of the new NE 128th bridge. Crews build a temporary wooden deck to support them while they build the permanent deck of steel and concrete. You can see the NE 124th bridge in the distance.