I-205 Mill Plain/112th Street Connector

Project Description
This project will provide a direct connection to NE 112th Avenue from the off ramp of northbound I-205 to westbound Mill Plain Boulevard. It is a partnership project with the City of Vancouver.

Contractor/Consultant
Skillings-Connolly Inc.   

Recent Progress

Skillings-Connolly Inc. has been hired as a consultant to assist WSDOT in the design phase of this project.  The scope of  this work is currently being defined and negotiated.

Design Construction Impacts
At this time there are no known design issues that will impact the scope, schedule or budget for this project.

Environmental Impacts / Compliance
Impacts are unknown at this time.

Impacts to Traffic
None at this time.

Project Milestones Scheduled Attained Milestone Outlook
Design Start September 2003 December 2003 Design phase has started.
Record of Decision April 2005 No issues at this time.
Right of Way Complete March 2006 No issues at this time.
Ad Date April 2006 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 1.0 7.4
Right-of-Way 0.5 3.7
Construction 12 88.9
Funded Project Costs 13.5 100

Nickel funds included in above costs

12 88.9

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects