Project Title & Location
I-205 / Mill Plain Interchange to NE 18th Street
|
Project Description
This project will improve safety and mobility in the area by constructing a new I-205 northbound off-ramp and southbound on-ramp at NE 18th Street and providing grade separated ramp connections.
|
|
Contractor/Consultant
|
|
Recent Progress
NEPA was completed in 2007. The project will proceed with critical right of way acquisition. Design activities will commence in 2009-2011.
|
|
Design Construction Impacts
Construction is currently scheduled for Spring/Summer of 2014 through 2016. Impacts are anticipated at Mill Plain, 9th Street, 18th Street and I-205.
|
|
Environmental Impacts / Compliance
Environmental documentation for this project and the I-205 Mill Plain Exit-112th Connector was completed in August 2007.
|
Impacts to Traffic
The design team will generate effective staging plans to minimize construction impacts to the traveling public. To be further evaluated as the design advances.
|