I-182 - US 395 Interchange - Complete September 2003

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location

I-182/US 395 I/C Roadside Safety –

Richland Vicinity

Project Description
This project will reduce the severity of run-off-the-road accidents at this location by adding a widened and flattened slope on the outside of the loop ramp carrying traffic from westbound I-182 to southbound US 395.

Contractor/Consultant
Transtate Paving Company - Tri-Cities, WA

Recent Progress

Construction on this project started September 2, 2003 and was completed on September 18, 2003.  The anticipated construction cost for this project is $76,222, 24% below the engineers’ estimate of $100,011.

Design Construction Impacts

There were no Design or Construction impacts on this project. 

Environmental Impacts / Compliance

There were no Environmental impacts on this project.  The slope protection rock was placed on the new slope immediately after it was constructed and seeding took place a week later.

Impacts to Traffic

The ramp shoulders were closed during the duration of this project with little impact to traffic.

Project Milestones Scheduled Attained Milestone Outlook
Contract Advertised Jul 03 Jul 03 Completed on time.
Contract Awarded Sep 03 Aug 03 Completed 3 weeks ahead of schedule.
Groundbreaking Oct 03 Sep 03 Began work on September 2, 2003, one month ahead of schedule.
Open to Traffic Feb 04 Sep 03 Project was open to traffic on Sept. 12, 2003, 4 months ahead of schedule.  Seeding was completed on Sept. 18, 2003.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.01 11.5%
Right-of-Way 0
Construction $0.08 88.5%
Funded Project Costs $0.09 100%

Nickel funds included in above costs

$0.08 88.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Moe Davari, WSDOT Project Engineer @ (509) 577-1872 Or E-mail: DavariM@wsdot.wa.gov