Project Title & Location
I-182/US 395 I/C Roadside Safety – Richland Vicinity
|
Project Description
This project will reduce the severity of run-off-the-road accidents at this location by adding a widened and flattened slope on the outside of the loop ramp carrying traffic from westbound I-182 to southbound US 395.
|
|
Contractor/Consultant
Transtate Paving Company - Tri-Cities, WA
|
|
Recent Progress
Construction on this project started September 2, 2003 and was completed on September 18, 2003. The anticipated construction cost for this project is $76,222, 24% below the engineers’ estimate of $100,011.
|
|
Design Construction Impacts
There were no Design or Construction impacts on this project.
|
|
Environmental Impacts / Compliance
There were no Environmental impacts on this project. The slope protection rock was placed on the new slope immediately after it was constructed and seeding took place a week later.
|
Impacts to Traffic
The ramp shoulders were closed during the duration of this project with little impact to traffic.
|