 |
• Report Home • Evaluation Criteria
|
 |
 |
 |
Project Evaluation: I-5, I-205 to N. Fork Lewis River Bridge
Clark County This 12-mile long concrete stabilization and rehabilitation project starts at the I-205 merge in the Salmon Creek area of the county and extends to the North Fork Lewis River Bridge at the Cowlitz County line near the city of Woodland. This project will stabilize the existing concrete pavement in all lanes by tying the individual concrete panels to each other using steel dowel bars, replace over 150 damaged concrete panels, and grind smooth the tire ruts on selected sections. This will give drivers a smoother ride, extend the life of the existing concrete pavement, and upgrade all safety features in both directions of I-5 to current standards.
 |

Design: None, project delayed to 2006
Construction Management: None, project delayed to 2006
Schedule: None, project delayed to 2006
Cost – None, project delayed to 2006
-
Engineer’s estimate: Not applicable
-
Contractor’s bid amount: Not applicable
-
Anticipated final payment to contractor: Not applicable
|
Construction Summary: This project was not awarded in 2005. It was advertised for bids twice in summer 2005, and both times the apparent low bid was approximately 30% over our engineer’s estimate. In each case we rejected all the bids and decided to not award the contract. After the first bid opening, we made some adjustments to the design as new information became available. Ultimately, we decided to wait until later in the year to advertise a third time due to the possibility that an off-season advertisement might yield more competitive bids. The current ad date is scheduled for December 5, 2005. If the contract is awarded, construction would likely begin in spring 2006.
Contact Information Contractor: None – project delayed to 2006
WSDOT Contact:
Casey Liles, Vancouver Area Engineer
360-905-1500
swvanc@wsdot.wa.gov
back to top
|