2004 Construction Highlights Report

There's a familiar saying at the Washington State Department of Transportation: “What gets measured, gets managed." WSDOT’s 2004 Construction Highlights Report is a self-evaluation of 25 construction projects that were underway and/or completed during the 2004 construction season.  The report allows each project office to make a critical assessment of their performance and project delivery, bringing to light both lessons learned and successes to share.

Projects were selected in April 2004, prior to the start of construction for most. These represent a variety of types of projects such as bridge repair, highway resurfacing, interchange construction, etc., which are constructed in a range of environments – from the farmlands of Eastern Washington, to the foothills of the Cascade Mountains, to Washington’s major urban areas, to the rain forests of the Olympic Peninsula.

Our evaluation standards focus on design, contract administration, schedule and budget, and rates each of these elements.  The ratings take into account how well the contract was designed – was it constructed as planned, or did it require major changes that impacted cost and schedule?  Did WSDOT and the contractor work as a team, or did communication difficulties get in the way of delivering the project?  Did the project stay on schedule and was inconvenience to the public kept to a minimum?  How did the project’s final construction cost compare to the engineer’s estimate and contractor’s original bid amount?

These are just a sampling of the many projects that were built during the 2004 construction season to improve Washington’s state highways and Interstate freeways. From January through September 2004, WSDOT and its contractors launched 114 highway construction projects.  These represent $238,973,190 in winning contractor’s bids and compare with $240,095,713 in WSDOT Engineer’s Estimates.

Highway Construction Project Rating for 2004 Season

Project

Design

Contract Admin

Schedule

Cost

I-405 Bellevue Direct Access  5 Stars  5 Stars  5 Stars  5 Stars
I-5, Ash Way Park & Ride Direct Access

 3 Stars

 3 Stars  1 Star  2 Stars
I-5, Lynnwood Park & Ride Access Improvement  5 Stars  5 Stars  5 Stars  5 Stars
I-5, Nisqually River Bridge to Fort Lewis  5 Stars  4 Stars  2 Stars  4 Stars
I-5, Ramps at Michigan-Corson, Albro, Swift  3 Stars  4 Stars  2 Stars  3 Stars
I-90, Adams County Line to Spokane County Line  4 Stars  5 Stars  4 Stars  5 Stars
Icon indicating Nickel Project  I-90, Highline Canal to Elk Heights  3 Stars  4 Stars  5 Stars  3 Stars
I-90, Moses Lake West Paving  5 Stars  5 Stars  5 Stars  5 Stars
I-90, Tibbetts Creek Vic. Culvert Replacement 4 Stars  5 Stars  5 Stars  4 Stars
SR 124, East Jct. US 12 - Reconstruction  5 Stars  5 Stars  5 Stars  5 Stars
SR 127, Central Ferry to Church Hill Road  5 Stars  5 Stars  5 Stars  5 Stars
SR 129, Clarkston Vicinity Paving  5 Stars  5 Stars  5 Stars  5 Stars
SR 16, 6th Avenue to Jackson Avenue HOV  4 Stars  4 Stars  5 Stars  5 Stars
SR 167, North Sumner Interchange  4 Stars  5 Stars  5 Stars  5 Stars
SR 20, Oak Harbor North City Limits  4 Stars  4 Stars  3 Stars  4 Stars
Icon indicating Nickel Project  SR 203, NE 124 - Novelty Rd. Vic. Roundabout  3 Stars  5 Stars  5 Stars  3 Stars
SR 28, Harrington to Davenport - Paving  5 Stars  5 Stars  5 Stars  5 Stars
SR 433, Lewis and Clark Bridge - Deck Replacement  3 Stars  5 Stars  4 Stars  3 Stars
SR 502, I-5 to Battle Ground  5 Stars  5 Stars  5 Stars  5 Stars
SR 525, SR 99 to SR 526, Phase 2  2 Stars  4 Stars  2 Stars  2 Stars
SR 527, 164th St SE to 132nd St SE Additional Lanes  2 Stars  3 Stars  3 Stars  2 Stars
SR 970, Cle Elum Vicinity Paving  5 Stars  5 Stars  5 Stars  5 Stars
US 101, Sitkum-Sol Duc Rd. to Bear Creek Rd. Paving  4 Stars  5 Stars  4 Stars  5 Stars
US 12, Lake Creek to Wild Cat Creek  5 Stars  5 Stars  5 Stars  5 Stars
Wenatchee North Paving  5 Stars  5 Stars  5 Stars  5 Stars

Print-Friendly Version
Evaluation Criteria