2002 Project Highlights

WSDOT has wrapped up a season of construction projects to improve Washington's highways and Interstate freeways. Between January 1st and December 1st, WSDOT and its contractors have closed out 156 projects to rebuild interchanges and bridges, pave roads and make safety improvements across the state. For these 156 projects, the total of WSDOT engineer’s pre-bid estimates was $300.4 million. The total of the winning contractors' bids was $274.9 million. Final payments to contractors are right at $296 million. That's about 1.5% below our original engineer's estimates and about 7.7% above the total of the contractors’ bids.

This report card gives special attention to project performance in terms of cost and schedule, matters of great importance to the public and to the department’s performance accountability. However, as review of the specific project examples will show, these are not the only criteria by which projects should be judged. Other concerns include things like job quality and impacts to motorists. Indeed, sometimes schedules must be stretched or budgets grown when public input requires project revisions. The notes below will highlight specific experience in some of these areas.

WSDOT is working hard to account for our project delivery record to legislators, taxpayers and motorists. Below is a sampling of this summer’s projects.

   

Click on the stars to read the project results:

2002 State Map with locations of highlighted projects

Project Name

Location

Schedule

Cost

Comments

I-5 Tukwila to Pierce County Line
HOV Lane – Stage 3

King County

Good

Fair

Completed seven days ahead of schedule and is expected to come in about 8% over the engineer’s estimates of $28 million.

SR 500 Thurston Way

Vancouver

Good

Good

This is the state's first design build project. It was completed on schedule and on budget ($22.7 million).

SR 16, Sprague Avenue to Snake Lake

Tacoma

Poor

Poor

Deficiencies in the plan required redesign work and extended the project construction schedule by about 90 working days. The project is expected to come in about 12% over engineer’s estimates of $15.2 million.

I-5 Widening, 93rd Avenue to Maytown

Thurston County

Good

Good

Completed on time and approximately 6% under the $8.5 million engineer’s estimate.

SR 529, Steamboat Slough Bridge Rehabilitation

Everett

Good

Mixed

Completed ahead of schedule and 58% over the $8 million engineer’s estimates due principally to revised traffic mitigation plans and a larger incentive payment earned by the contractor for an early project finish.

SR 303, Phase 2 Safety Improvement

Kitsap County

Fair

Good

Work is expected to finish slightly over schedule and is expected to be 3% under engineers estimates of $4.1 million.

US 2, Hewitt Avenue Trestle

Snohomish County

Good

Mixed

Completed work requiring 24 hour lane closure 10.5 days ahead of schedule. Project costs were 79% over the engineer's estimate of $4.09 million. This was due in part to an increase of 30% over the contractor's bid amount for revised traffic plans and early completion objectives.

US 2, Deer Rd. to Westwood Rd. Paving

North of Spokane

Good

Good

Completed on time and is expected to come in approximately 20% under engineer’s estimates of $2.8 million.

SR 500, Vancouver - Burnt Bridge Creek to Andresen Road

Vancouver

Good

Good

Completed on time and is anticipated to come in 9% - 10% under engineer’s estimate of $2 million.

US 12, Cowiche Creek to I-82 Paving

Yakima County

Good

Good

Completed on time and 19% under the $1.9 million engineer’s estimate.

I-90, Harvard Rd. Interchange- Westbound Ramp Revisions

Liberty Lake, Spokane County

Good

Good

Completed on time and is anticipated to come in at about 22% under engineer’s estimate of $1,692,122.

I-5 Olive to Boylston Electrical Upgrade

Seattle

Good

Poor

Completed on time but about 20% over the $1.6 million engineer’s estimate.

I-5 Northgate Bridge Deck Repair

North Seattle

Good

Mixed

Completed three days ahead of schedule at about 20% over the $1,292,460 engineer’s estimate and also over the bid.

SR 127, Church Hill Rd to Dusty (SR 26) Paving

Whitman County

Good

Good

Completed on time and is anticipated to come in at about 15% under the $1.3 million engineer’s estimate.

I-5 Ramp Paving – South Tacoma To Fife

Pierce County

Good

Good

Completed on time and is expected to come in about 10% under engineer’s estimate of $1.06 million.

SR 507, Centralia – I-5 to Old Skookumchuck River Bridge

Lewis County

Good

Good

Completed on time and about 24% under the $800,697 engineer’s estimates.

SR 543, Boblett Street Signalization

Blaine

Good

Good

Completed on time and about 21% under engineer’s estimates of $714,442.

SR 153, Carlton Bridge Repair

Okanogan County

Good

Fair

Completed ahead of schedule and 8% over the $484,508 engineer’s estimate.

US 97, Tonasket-Bonapart Creek Bridge Deck

Okanogan County

Good

Good

Completed on time and approximately 0.7% under engineer’s estimate of $153,568.

I-82, Ellensburg/Selah Area Variable Message Signs

Yakima County

Good

Mixed

Completed on time and approximately 13% over the $119,374 engineer’s estimates.

SR 500, NE 124th Ave. Intersection
– Safety Improvements

Clark County

Good

Good

Completed on schedule and approximately .2% under the engineer’s estimate of $86,664.

Washington State Ferries Terminal Project

Kingston Ferry Terminal, Phase 2
Dolphin Replacements

Kitsap County

Good

Good

Completed ahead of schedule and 12% under engineer’s estimates of $1.7 million.