
Schedule: Good The contractor had 155 days to complete the dolphins and finished work in 134 days.
Cost: Good Engineer’s estimate: $1,781,703
Contractor’s bid amount: $1,429,121.
Final payment: $1,560,256
The variance between the engineer’s estimate and the final payment was primarily due to savings in structural steel and pile driving costs. The variance between the bid amount and the final payment was primarily due to emergency repairs of damage to pier structures caused by ferries and increasing the pile lengths during the construction period.
|