US 12 Black River Bridge Column Protection - Gray's Harbor County


Report Card

On time: Good
The project was completed 15 days ahead of schedule

On Budget: Good
The project came in $6,000 under the $103,000 budget.

The US 12 Black River Bridge provides a vital connection between SR 8 and I-5 in Grays Harbor County. That connection was threatened, however, due to riverbed erosion around the bridge columns that threatened their stability. Without protective measures, there was a danger the bridge could fail

To maintain this important connection, the contractor, Northwest Rock, placed rock around the columns and to stabilize the bank to prevent further erosion. Working in the river without harming habitat can be a tricky thing - WSDOT and the contractor closely coordinated with the Departments of Fish and Wildlife and Ecology to ensure minimal impacts to water quality and river habitat.

Other notes:
Cooperation with the contractor, Fish and Wildlife, and Ecology was critical to ensure that environmental goals were met and which ultimately allowed the project to come in early and under budget.