US 12 - Tucker Road Intersection - Lewis County


Report Card

On time: Good
The work was completed on time.

On Budget: Good
The project was $9,000 (less than two percent) over its $503,000 budget.

This safety project helped reduce the problem of frequent fender benders and rear end collisions from people slowing on the highway to make a left turn onto Tucker Road. A bridge was extended, which allowed us to realign the highway and provide enough space for a turn lane.

James Dean Construction worked hard to preserve the environment, temporarily rerouting a stream to prevent construction debris from entering the water during the bridge-widening effort.