• 2001 Project Highlights • Map of Projects
|
 |
 |
 |
I-90 Sprague Avenue Interchange Reconstruction - Spokane
 |

On time: Good The work was completed in one construction season, and about a month early
On Budget: Good The project was on budget at $14.6 million
|
When the interchange opened in late September, it was the completion of four separate projects to reconstruct I-90 between Havanna and Argonne. This last phase is a great example of how WSDOT and private contractors can work together to complete projects ahead of schedule. By heating and covering the concrete as it cured, the Max J. Kuney Company was able to finish the job in one construction season instead of two.