I-82 Plastic Centerline Stripe - Yakima to Umatilla
 |

On time: Good The work was completed 27 days early.
On Budget: Good The project was $35,443 under the $926,100 budget.
|
The 95 miles between Umatilla and Yakima may not look different from other highways, but a project to install plastic centerline striping this year will save money, increase safety, and free up maintenance crews to work on other projects. Most road stripes are made from latex paint. This one is a plastic product that not only lasts longer, but is more visible to motorists.