SR 14 Lyle Tunnel Repairs |
Klickitat County |
Poor |
Poor |
Additional tasks needed to ensure safety added 3 months and a 30% increase in costs. |
|
I-5 and SR 501 Paver |
Vancouver |
Good |
Good |
Completed on time and $26,720 under budget |
|
US 12 Intersection Improvements |
Tucker Road - Lewis County |
Good |
Good |
Completed on time and less than 2% over its $503,000 budget. |
|
Highway 512 Paving Contract |
Puyallup |
Good |
Good |
14 days ahead of schedule; $230,000 under budget |
|
US 12 Bridge Column Protection |
Black River Bridge- Gray's Harbor County |
Good |
Good |
15 days ahead of schedule; The project came in $6,000 under the $103,000 budget. |
|
SR 105 Bridge Deck Rehabilitation |
Elk River - Bay City |
Good |
Good |
9 days ahead of schedule; $84,000 under budget |
|
I-405 HOV Lanes |
Bothell to Swamp Creek |
Good |
Fair |
WSDOT estimates the job will be finished 8 to 12 months early, and 5% over budget |
|
SR 99 Interchange at SR 525 |
Snohomish County |
Good |
Fair |
Opened 3 months ahead of schedule; $1.2 million over budget due to hazardous materials clean-up |
|
SR 529 - Steamboat Slough Bridge |
Everett |
Good |
Poor |
The project was done on time, but WSDOT could not safely keep the bridge open while the mechanical parts were being repaired, so the bridge was closed, creating traffic tie ups. |
|
I-5 Bridge Deck Rehabilitation |
Ravenna Street - Seattle |
Good |
Good |
Opened 3 days early and came in $22,390 under budget |
|
SR 20 Bridge Replacement |
Damnation Creek - East of Concrete |
Good |
Good |
Project nearing completion. Pre-construction decisions resulted in an accelerated schedule, should allow the bridge to be completed in one construction season. |
|
SR 285 Bridge Painting |
Wenatchee River - Chelan County |
Good |
Good |
Completed 4 weeks early and $18,000 under budget |
|
SR 150 Safety Improvements |
Boyd and Dietrich Roads - Chelan County |
Good |
Good |
Opened 2 weeks early and $75,000 under budget |
|
I-82 Striping |
Yakima to Umatilla |
Good |
Good |
Completed 27 days early and $35,443 under budget |
|
I-90 Glare Screen |
Snoqualmie Pass |
Good |
Fair |
21 days early and $20,000 over budget |
|
SR 27 and 272 Reconstruction |
Palouse |
Good |
Good |
On-time and 5% under budget |
|
I-90 Interchange |
Sprague Avenue - Spokane |
Good |
Good |
Project was completed at least 30 days ahead of schedule and on-budget |
|
US 395 Rumble Strips |
North Spokane to Loon Lake |
Good |
Good |
The project was on time and on budget at $80,700. |