2001 Project Highlights

WSDOT is wrapping up a season of construction to improve Washington's highways and Interstate freeways. Since January 1st, WSDOT and our contractors have completed 88 projects to rebuild interchanges and bridges, pave roads and make safety improvements across the state. For these 88 projects, the total of our engineers' estimates were $141.6 million and the total of the winning contractors' bids was $126.5 million. Our final contractor payments were just under $130 million. That's about 2.5% over the prices at which the work was awarded to the contractor.

WSDOT is working hard to demonstrate to legislators, taxpayers and motorists our success in delivering projects. We think our record is worth sharing. Below is a sampling of projects that demonstrate our ability to get the job done.

This construction season also highlighted areas where we need improvement. Severe traffic tie ups in Everett from our SR 529 bridge work show we can do better on traffic management and communications with those affected by our work.

Click on the stars to read the project results:

2001 State Map with locations of highlighted projects

 

Project Name

Location

On Time

On Budget

Comments

SR 14 Lyle Tunnel Repairs

Klickitat County

Poor

Poor

Additional tasks needed to ensure safety added 3 months and a 30% increase in costs.

I-5 and SR 501 Paver

Vancouver

Good

Good

Completed on time and $26,720 under budget

US 12 Intersection Improvements

Tucker Road - Lewis County

Good

Good

Completed on time and less than 2% over its $503,000 budget.

Highway 512 Paving Contract

Puyallup

Good

Good

14 days ahead of schedule; $230,000 under budget

US 12 Bridge Column Protection

Black River Bridge- Gray's Harbor County

Good

Good

15 days ahead of schedule; The project came in $6,000 under the $103,000 budget.

SR 105 Bridge Deck Rehabilitation

Elk River - Bay City

Good

Good

9 days ahead of schedule; $84,000 under budget

I-405 HOV Lanes

Bothell to Swamp Creek

Good

Fair

WSDOT estimates the job will be finished 8 to 12 months early, and 5% over budget

SR 99 Interchange at SR 525

Snohomish County

Good

Fair

Opened 3 months ahead of schedule; $1.2 million over budget due to hazardous materials clean-up

SR 529 - Steamboat Slough Bridge

Everett

Good

Poor

The project was done on time, but WSDOT could not safely keep the bridge open while the mechanical parts were being repaired, so the bridge was closed, creating traffic tie ups.

I-5 Bridge Deck Rehabilitation

Ravenna Street - Seattle

Good

Good

Opened 3 days early and came in $22,390 under budget

SR 20 Bridge Replacement

Damnation Creek - East of Concrete

Good

Good

Project nearing completion. Pre-construction decisions resulted in an accelerated schedule, should allow the bridge to be completed in one construction season.

SR 285 Bridge Painting

Wenatchee River - Chelan County

Good

Good

Completed 4 weeks early and $18,000 under budget

SR 150 Safety Improvements

Boyd and Dietrich Roads - Chelan County

Good

Good

Opened 2 weeks early and $75,000 under budget

I-82 Striping

Yakima to Umatilla

Good

Good

Completed 27 days early and $35,443 under budget

I-90 Glare Screen

Snoqualmie Pass

Good

Fair

21 days early and $20,000 over budget

SR 27 and 272 Reconstruction

Palouse

Good

Good

On-time and 5% under budget

I-90 Interchange

Sprague Avenue - Spokane

Good

Good

Project was completed at least 30 days ahead of schedule and on-budget

US 395 Rumble Strips

North Spokane to Loon Lake

Good

Good

The project was on time and on budget at $80,700.

US 12 Intersection ImprovementsHighway 512 Paving ContractSR 105 Bridge Deck RehabilitationI-405 HOV LanesSR 99 Interchange at SR 525I-5, Ravenna St. Bridge Deck RehabilitationPauloseI-82 Striping, Yakima to UmitillaSR 285 Bridge Painting SR 150 Safety ImprovementsI-90 Anti-Glare ScreenI-5, 501 RepaveI-90 Sprague InterchangeLyle St TunnelSR529  - Steamboat SloughSR20 Damnation CreekUS395 Rumble Strips