Construction and maintenance closures for Friday, Feb. 1, - Sunday, Feb. 10, 2013

Last updated: Friday, Feb. 1, 2013, 1:18 p.m.

This information changes frequently. Please check back often. Travelers can also call 5-1-1 for real-time traffic and weather updates.

If you have questions or comments that are not addressed by these resources, please contact the Communications Office at 206-440-4697.



Choose your highway:

| US 2  | I-5  | SR 9 SR 522 | SR 525 | SR 529

Other traffic interests:

Special Events 

Last update: 7:50 a.m., 1/31
US 2 - Bickford Avenue interchange safety and culvert replacement #8286
Mileposts 2-4
Mark Sawyer, Project Engineer, 425-225-8799
Get project information

  • Monday, Feb. 4 to the morning of Tuesday, Feb. 5 - Westbound US 2 will be closed between SR 9 and SR 204 at the trestle from 8 p.m. to 5 a.m. for work on the new overpass. The SR 9 on-ramp to westbound US 2 will also be closed from 7 p.m. to 5 a.m. Westbound drivers will exit to northbound SR 9 and then turn west on 20th Street Southeast to return to US 2.
  • Monday, Feb. 4 to the morning of Tuesday, Feb. 5 -  Eastbound US 2 will be reduced to one lane at Bickford Avenue from 7 p.m. to 5 a.m. for work on the new overpass
  • Monday, Feb. 4 to the morning of Tuesday, Feb. 5 - Bickford Avenue will be closed from 7 p.m. to 5 a.m. for work on the new overpass at US 2.
  • Driver alert: The existing eastbound US 2 off-ramp to Bickford Avenue is closed until fall 2013. Drivers can exit to Bickford Ave. using a temporary right-turn lane near the intersection. 

Last update: 1:18 p.m., 2/1
US 2: SR 522 interchange - widening and safety #7938
Mileposts: 24.14
Janice Fahning , Project Engineer, 425-225-8700
Get project information

  • Monday, Jan. 28 to Friday, Feb. 1 - We do not expect construction to affect traffic on US 2 this week. 
  • Monday, Feb. 4 to Friday, Feb. 8 - We do not expect construction to affect traffic on US 2 this week.
  • There may also be closures on SR 522.

I-5  

 

Last update:  9:10 a.m., 2/1
I-5: Lakewood Triangle Access/156th Street Overcrossing
Milepost: 205.07
Pat Gruenhagen, City of Marysville Project Engineer, 360-363-8279 

  • Monday, Jan. 28 to Friday, Feb. 1 - We do not expect work to affect traffic this week.
  • Monday, Feb. 4 to Friday, Feb. 8 - We do not expect work to affect traffic this week.

 

SR 9    

Last update: 3:33 p.m., 1/31
SR 9: 176th St. SE to SR 96 paving #8268
Mileposts: .78
John Chi, project engineer, 425-225-8741
Get project information

  • Monday, Jan. 28 - Friday, Feb. 1 - We do not expect work to affect traffic this week.
  • Monday, Feb. 4 - Friday, Feb. 8 - We do not expect work to affect traffic this week.


Last update:  3:33 p.m., 1/31
SR 9: 212th Street Southeast to 176th St. SE stage 3 widening #8140
Mileposts: 1.6 to 4.03
John Chi, project engineer, 425-225-8741
Get project information

  • Monday, Feb. 4 to the morning of Tuesday, Feb. 5 - One lane of SR 9 between 180th and 201st may close and traffic will be flagged at all intersections from 8 p.m. to 5 a.m. for striping. This work is weather dependent.

Last update: 3:33 p.m., 1/31
SR 9: Wetland mitigation #8184
Mileposts: .78
John Chi, project engineer, 425-225-8741

  • Monday, Jan. 28 - Friday, Feb. 1 - We do not expect work to affect traffic this week.
  • Monday, Feb. 4 - Friday, Feb. 8 - We do not expect work to affect traffic this week.

Last update: 7:50 a.m., 1/31
US 2 / SR 9 - Bickford Avenue interchange safety and culvert replacement #8286
Mileposts: US 2 - 2-4
Mark Sawyer, Project Engineer, 425-225-8799
Get project information

  • Monday, Feb. 4 to the morning of Tuesday, Feb. 5 - The SR 9 on-ramp to westbound US 2 will be closed from 7 p.m. to 5 a.m. due to work at the new overpass at Bickford Avenue.

 


  


SR 522  

Last update 9:10 a.m., 2/1
SR 522: Snohomish River Bridge to US 2- widening and safety #8128
Mileposts: 20 - 24.14 
Janice Fahning, Project Engineer, 425-225-8700
Get project information

  • Monday, Feb. 4 to the morning of Friday, Feb. 8 - A single lane of SR 522 will close nightly from 9 p.m. to 5 a.m. between Fales Road to east of the Snohomish River Bridge for construction work. Traffic will alternate in the open lane.
  • February blasting schedule: SR 522 between Fales/Echo Lake roads and 164th Street Southeast will be closed from 10:15 to 11:15 a.m. for rock blasting on the following dates: Friday, Feb. 1, Tuesday, Feb. 5, Thursday, Feb. 7, Tuesday, Feb. 12, Thursday, Feb. 14, Tuesday, Feb. 19, Thursday, Feb. 21, Tuesday, Feb. 26, Thursday, Feb. 28.  Drivers will follow a signed detour using SR 9 and US 2. The detour will add 10 miles and 20 minutes to trips, depending on destination and traffic.

Last update: 1:18 p.m., 2/1
US 2: SR 522 interchange - widening and safety #7938
Mileposts: 24.14
Janice Fahning , Project Engineer, 425-225-8700
Get project information

  • Monday, Feb. 4 to Friday, Feb. 8 - No closures are planned at this time.

 

SR 529  

Last update: 9:10 a.m., 2/1
SR 529 Ebey Slough Bridge Replacement #7948
Mileposts 5.75 - 6.5 
Mark Sawyer, Project Engineer, 425-225-8799  
Get project information

  • Monday, Jan. 28 to Friday, Feb. 1 - We do not expect work to affect traffic this week.
  • Monday, Feb. 4 to Friday, Feb. 8 - We do not expect work to affect traffic this week.

 

 

 

  • None reported