I-5: Federal Way to Blaine Construction

Last update: 7:05 a.m. Monday, May 21

This information changes frequently. Please check back often. Travelers can also call 5-1-1 for real-time traffic and weather updates. 

King County | Snohomish County | Skagit County | Whatcom County

Express Lanes Schedule Changes

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 165.29 - 172.43
Contact: Nicole Daniels, Communications, 206-440-4479
Description: The I-5 express lanes are used to assist the flow of traffic during busy travel times. These lanes are scheduled to move in the direction that will relieve the most congestion from the transportation system.
Express lanes schedule
Work schedule:

  • **HIGH IMPACT** Saturday, June 2 & Sunday, June 3 - The northbound I-5 express lanes will be closed all weekend for "Revive I-5" construction work. The lanes will be open in the southbound direction from 8 a.m. to 11 p.m. daily.
NB S 260th St to Duwamish River Br Concrete Pavement Rehab & ADA - #8992

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 147.64 – 156.51
Contact: Mike Askarian, Project Engineer, 206-768-5861
Description: WSDOT contractor crews are rehabilitating northbound I-5 between South 260th Street in Des Moines and the Duwamish River Bridge in Tukwila.
Project webpage
Work schedule:

  • Monday, May 21, to the morning of Friday, May 25 - Up to three lanes of northbound I-5 between SR 516 and the Duwamish River Bridge will be closed beginning at 8 p.m. nightly. All lanes will reopen by 5 a.m. This work is weather dependent.
S 188th St to NE 80th St Camera Installation - #9147

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 152.80 - 172.25
Contact: Mark Sawyer, Project Engineer, 425-225-8799
Description: WSDOT contractor crews are installing cameras along I-5 between South 188th Street in SeaTac and Northeast 80th Street in Seattle.
Work schedule:

  • No lane or ramp closures are scheduled.
NB MLK Jr Way to NE Ravenna Br Pavement Repair - #8952

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 157.44 - 170.28
Contact: Dave Lindberg, Project Engineer, 425-225-8725
Description: WSDOT contractor crews are replacing 37 expansion joints and large sections of concrete pavement on northbound I-5 between MLK Junior Way South/SR 900 in Tukwila and Northeast Ravenna Boulevard in Seattle.
Project webpage
Work schedule:

LANE CLOSURES

  • Monday, May 21, to the morning of Friday, May 25 - Up to three lanes of northbound I-5 between the West Seattle Bridge and SR 520 will be closed beginning at 8 p.m. nightly. All lanes will reopen by 5 a.m. This work is weather dependent.

RAMP CLOSURES

  • Monday, May 21, to the morning of Friday, May 25 - The University Street on-ramp to northbound I-5 will be closed from 9 p.m. to 5 a.m. nightly. This work is weather dependent.
  • Monday, May 21, to the morning of Friday, May 25 - The northbound I-5 off-ramp to Seneca Street will be closed from 9 p.m. to 5 a.m. nightly. This work is weather dependent.
SB S Lucile St to Spring St Pavement Repair & ADA - #9235

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 161.68 - 165.62
Contact: Mike Askarian, Project Engineer, 206-768-5861
Description: WSDOT contractor crews are replacing broken concrete panels, grinding and repaving southbound I-5 and the collector/distributor between Spring Street and South Lucile Street in Seattle.
Project webpage
Work schedule:

  • Construction is scheduled to begin in spring 2018.
Sound Transit's East Link Extension - E130

Highway: I-5    RegionNorthwest    County: King    Location: Milepost(s) 164.00
Contact: Zack Ambrose, Sound Transit, 206-903-7176
Description: Sound Transit crews are constructing the East Link light rail extension from Seattle to Redmond.
Project webpage
Work schedule:

  • No lane or ramp closures are scheduled.
Express Lanes Entrances Electronic Sign Replacement 

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 165.39 - 172.61
Contact: Dave Lindberg, Project Engineer, 425-225-8725
Description: WSDOT contractor crews are replacing the sign structures and brackets, along with the electrical and fiber optic systems at seven entrances to the I-5 express lanes. A few of the sign structures will also be redesigned to create a better viewing angle.
Project webpage
Work schedule:

  • Construction is scheduled to begin in spring 2018.
Ship Canal Bridge Deck Repair Work

Highway: I-5    Region: Northwest    County: King    Location: Milepost(s) 168.00
Contact: Nicole Daniels, Communications, 206-440-4479
Description: WSDOT maintenance crews are performing deck repair work on the I-5 Ship Canal Bridge in downtown Seattle.
Work schedule:

  • **HIGH IMPACT** Saturday, June 2 - Southbound I-5 traffic will be reduced to two lanes across the Ship Canal Bridge from 2 a.m. to noon. This work is weather dependent.
  • **HIGH IMPACT** Sunday, June 3 - Southbound I-5 traffic will be reduced to two lanes across the Ship Canal Bridge from 2 to 11 a.m. This work is weather dependent.
  • **HIGH IMPACT** Sunday, June 3 - The Northeast 45th Street on-ramp to southbound I-5 will be closed from 2 to 11 a.m. This work is weather dependent.
Ebey Slough Bridge to SR 531 Interchange Paving & ADA Compliance - #9028

Highway: I-5    RegionNorthwest    County: Snohomish    Location: Milepost(s) 198.50 – 200.50
Contact: Mark Sawyer, Project Engineer, 425-225-8799
Description: WSDOT contractor crews are repaving an 8-mile stretch of southbound I-5 between SR 531 and SR 529, and about 7-miles of northbound I-5 between SR 529 and 136th Street Northeast in Marysville.
Project webpage
Work schedule:

  • Monday, May 21, to the morning of Friday, May 25 - The two left lanes of southbound I-5 between the Ebey Slough Bridge and 116th Street Northeast will be closed beginning at 7 p.m. nightly. All lanes will reopen by 5 a.m.
116th St NE Interchange - Tulalip Tribes Lead

Highway: I-5    RegionNorthwest    County: Snohomish    Location: Milepost(s) 202.20 – 202.70
Contact: Mark Sawyer, Project Engineer, 425-225-8799
Description: Tulalip Tribes contractor crews are reconstructing the I-5/116th Street Northeast interchange in Marysville.
Project webpage
Work schedule:

  • No lane or ramp closures are scheduled.
Stillaguamish River Br to Hill Ditch Br Paving & ADA Compliance - #9231

Highway: I-5    Region: Northwest    County: Snohomish    Location: Milepost(s) 209.09 - 219.82
Contact: Shane Spahr, Project Engineer, 360-848-7103
Description: WSDOT contractor crews are repairing 10 miles of concrete on northbound I-5 between Arlington and Conway.
Project webpage
Work schedule:

  • Construction is scheduled to begin in spring 2018.
Stanwood to Mount Vernon Area - Northwest Washington Cable Barrier Upgrades - #9144

Highway: I-5    Region: Northwest    County: Snohomish/Skagit    Location: Milepost(s) 215.12 - 225.48 and 230.90 - 234.61
Contact: Shane Spahr, Project Engineer, 360-848-7103
Description: WSDOT contractor crews from Petersen Brothers are upgrading nearly 40 miles of median cable barrier on six different highways in four different counties. Work on each stretch will take about two weeks and the contractor will complete one section before moving on to the next. Neighbors living near the work zones will hear a drill rig, which often sounds like a vehicle revving its engine, drilling, clunking and thudding as bases and posts are put into place. If you have noise complaints about this project, call the toll-free noise hotline at 1-888-808-4DOT (4368).
More project information
Work schedule:

  • No lane or ramp closures are scheduled.

Bow Area - WSDOT Maintenance Work

Highway: I-5 Region: Northwest County: Skagit Location: Milepost(s) 236
Contact: Andrea Petrich, Communications, 360-757-5963
Description: Crews will perform maintenance work.
Work schedule:

  • Tuesday, May 22, to the morning of Wednesday, May 23 - Crews will close the left lane of southbound I-5 at Bow Hill Road and the southbound on-ramp to I-5 at Bow Hill from 9 p.m. to 5 a.m. for annual maintenance.

Lake Samish Vicinity Stormwater Pipe Replacement - #9161

Highway: I-5    Region: Northwest    County: Skagit/Whatcom    Location: Milepost(s) 241.37 - 246.25
Contact: Gabe Ng, Project Engineer, 360-788-7403
Description: WSDOT contractor crews from Faber Construction are improving culverts and drainage along I-5 between Burlington and Bellingham.
Work schedule:

  • Work on this project is suspended until June 15 when DFW permits allow crews to work under the high water line.
  • No lane or ramp closures are scheduled.