Repairs complete, SR 520 pontoon headed home

Get Our Mobile App

  • Our Android and iPhone apps include statewide traffic cameras, travel alerts, mountain pass reports, ferry schedules and alerts, northbound Canadian border wait times and more.

Date:  Friday, August 23, 2013

Contact: Debera Carlton Harrell, SR 520 Communications 206-770-3554, 206-819-7230 (mobile)

Photos of repairs and float-out available on Flickr

PORTLAND, Ore. – Construction crews completed repairs to a State Route 520 pontoon in a Portland, Ore., drydock facility, and now prepare it for its journey to Lake Washington.

Pontoon T was floated out of the Vigor-owned drydock Thursday, Aug, 22, and will be towed to Lake Washington, beginning tomorrow, Saturday, Aug. 24. Pontoon watchers can expect to see the massive concrete pontoon travel through the Hiram M. Chittenden Locks and the Lake Washington Ship Canal late next week.

The repairs, completed by Washington State Department of Transportation’s contractor Kiewit/General/Manson, A Joint Venture, addressed cracks that developed in the keel slabs and end walls on four of the first six pontoons built in Aberdeen as part of Cycle 1 construction.

Crews sealed cracks in Pontoon T by injecting epoxy, adding post-tensioning across the ends of the pontoon and applying a carbon-fiber wrap to portions of the keel slab. Post-tensioning is a common construction process in which steel cables are placed through the concrete and tightened to increase strength. The repairs, endorsed by an expert review panel, will help ensure that the new floating bridge meets its 75-year design life.

“The repairs were completed on schedule and we look forward to welcoming Pontoon T back to Lake Washington,” said Dave Becher, WSDOT construction manager for the Floating Bridge and Landings Project. “We’ll moor the pontoon on Lake Washington until it’s ready to be joined with other pontoons, forming the backbone of the new floating bridge.”

Repairs on a second pontoon, Pontoon W, are moving ahead at a Seattle drydock and are on track for completion in several weeks.

The existing bridge, which will be 50 years old this month, is vulnerable to earthquakes and windstorms and must be replaced. Construction on the replacement bridge began in April 2012, and pontoon construction is underway at two casting basins: one in Aberdeen and one in Tacoma. Thirty-two of the 77 pontoons needed to replace the bridge are complete.

More information about the SR 520 Bridge Replacement and HOV Program is available at http://www.wsdot.wa.gov/projects/sr520bridge.