SPOKANE – As of 2:30 p.m. on Thursday, May 22, SR 206 has been restored and emergency or residential traffic is being escorted through the site. The gravel surface is narrow with steep slopes. The culvert installation is complete and stable. Roadway reconstruction and slope protection will continue tomorrow.
Last Sunday, May 18th, snow runoff water overwhelmed culverts under the State Park equipment shed and the state highway and undermined the roadway, subsequently destroying about 1,000 feet of the route. An emergency contract was set up to perform temporary repairs to open the roadway for limited traffic. A project to fully rebuild the highway will be under construction and completed later this summer.