Date:
Wednesday, July 19, 2006
Contact:
Contacts: Jerry Moore, Project Manager, (360) 457-2575
Lisa Murdock, WSDOT Communications, (360) 357-2789
CLALLAM COUNTY–A project to repair pavement, replace culverts, and fill wheel ruts on 23 miles of SR 112 between West Twin Rivers to US 101 begins this week.
WSDOT awarded the project to Lakeside Industries for its low bid of $2.27 million.
As part of the contract, crews will also upgrade sidewalk wheelchair ramps, repair pavement, fill wheel ruts and overlay pavement on 1.6 miles of the westbound couplet of US 101 between Golf Course Road and Lincoln Street.
Overall work includes nighttime lane closures on US 101 (8 p.m. to 6 a.m.) and shoulder closures along with lane shifts during the day. Anticipated work hours on SR 112 are from 7 a.m. to 4 p.m. with single lane closures July through October.
For specific traffic impact information for this or other WSDOT projects, visit
www.wsdot.wa.gov/regions/olympic/construction/.
< Back to News Home