Design: Project Development | GSP & Amendments | Division 8
DIVISION8.GR8 MISCELLANEOUS CONSTRUCTION
01.GR8 EROSION CONTROL AND WATER POLLUTION
CONTROL
0103.GR8 Construction Requirements
0103A.GR8 (Treatment of pH for Concrete Work)
(April 3, 2006)
Include in all projects when pH monitoring is
a condition of a NPDES construction permits,
a 401 Water Quality Certification, or other
permit. Requires approval of Regional
Environmental Manager and Regional Construction
Manager. Must also use 01031A.GR8, 0105.GR8,
01031A1.GR5, 0105.GR5, 05031B.GR5, 0505.GR5,
023003.GB6, and 025A4.GB6.
01031.GR8 General
01031A.GR8 Submittals
(April 3, 2006)
Must include with 0103A.GR8, 0105.GR8, 01031A1.GR5,
0105.GR5, 05031B.GR5, 0505.GR5, 023003.GB6,
and 025A4.GB6.
010310.GR8 (Erodible Soil Central Basin)
(April 3, 2006)
Use for projects east of the Cascade
range in areas receiving 12 inches or
less annual precipitation. Do not use
if any portion of the project lies
in areas that receive more than 12
inches of annual precipitation. See
Washington Mean Annual Precipitation.pdf
for precipitation map.
010310A.GR8 Must use with 010311.GR8 or 010312.FR8.
010311.FR8 (Offsite Stormwater)
April 1, 2002)
Use when there are known locations where
stormwater enters the project site and it
is desired to prevent this stormwater from
flowing uncontrolled through the project site.
(1 fill-in)
010312.FR8 (Side Slope Treatment)
(April 1, 2002)
Use on projects where erodible soils are
anticipated and it is desired to have the
newly exposed slopes walked before final
erosion control can be accomplished, in
accordance with recommendation from
environmental office.
010302.GR8 Erosion Control Seeding, Fertilizing, and
Mulching
010302B.GR8 Seeding and Fertilizing
010302B1A.FR8 (Composition, proportion, quality and
application rate of grass seed)
(December 4, 2006)
Use in projects with roadside seeding.
(2 fill-ins) (Fill-ins with dollar
signs only are to be used as required.)
010302B1B.FR8 (Composition, proportion, quality and
application rate of grass seed)
(December 4, 2006)
Use this GSP when Source identified or
non-source identified seed is not required.
(3 fill-ins) (Fill-ins with dollar signs
only are to be used as required.)
010302B2.GR8 (Seeding by hand)
(January 3, 2006)
Must also use 010302B5.GR8.
Use in projects with seeding and
fertilizing of less than 1 acre,
the use of mechanical equipment would
not be cost effective, or on remote
projects with many small areas.
010302B3.FR8 (One application of fertilizer)
(January 3, 2006)
Use in projects requiring only
one application of fertilizer.
(4 fill-ins) (The fill-ins for the
fertilizer itself should be by consulting
the State Horticulturist, the Region
Landscape Architect, or Headquarters
Roadside and Site Development. Fill-in
$$4$$ should be 2/3 the amount of nitrogen
in fill-in $$1$$.)
010302B4.FR8 (More than one application of
fertilizer)
(January 3, 2006)
Must also use 010302B1.FR8.
Use in projects when the Region
Landscape Arch. or Horticult.
recommends more than one fertilizer
application.
(7 fill-ins) (The fill-ins for the
fertilizer itself should be by consulting
the State Horticulturist, the Region
Landscape Architect, or Headquarters
Roadside and Site Development. Fill-in
$$7$$ should be 2/3 the amount of nitrogen
in fill-in $$4$$.)
010302B5.GR8 (Fertilizing by hand)
(January 3, 2006)
Must include with 010302B2.GR8.
Use in projects with seeding and
fertilizing of less than 1 acre,
the use of mechanical equipment
would not be cost effective, or
on remote projects with many small
areas.
010302B6.FR8 (Fertilizing by hand)
(January 3, 2006)
Must include with 010302B2.GR8.
Use this GSP for projects in eastern
Washington where soils tests show
excess potassium and phosphorous and
high pH.
010302C.GR8 Liming
010302C1.FR8 (Rate of application of lime)
(January 3, 2006)
Use in projects requiring the
application of lime.
(1 fill-in)
010302D.GR8 Mulching
010302D1.FR8 (Type and rate of application of mulch)
(January 3, 2006)
Use in projects requiring the
application of mulch.
(2 fill-ins)
0105.GR8 Payment
(April 3, 2006)
Must include with 0103A.GR8, 01031A.GR8,
01031A1.GR5, 0105.GR5, 05031B.GR5, 0505.GR5,
023003.GB6, and 025A4.GB6.
02.GR8 ROADSIDE RESTORATION
0201.GR8 Description
02012.GR8 (Removal of Buried Man-Made debis)
(December 6, 2004)
Use on projects that include soil amendment,
and/or irrigation systems, and where man-made
construction debris is known or suspected to
exist. Requires the approval of the Region
Construction Manager. Must include 0203052.GR8
and 02052.GR8.
0203.GR8 Construction Requirements
020305.GR8 Planting Area Preparation
0203051.FR8 (Application of compost)
(August 2, 2004)
Include when no incorporation of compost is
required.
(1 fill-in)
0203051A.FR8 (Application of compost)
(August 2, 2004)
Include when compost is to be incorporated into
the soil.
(2 fill-ins)
0203052.GR8 (Removal of Buried Man-Made Debris)
(December 6, 2004)
Must include with 02012.GR8 and 02051.GR8.
0205.GR8 Payment
02051A.GR8 (Compost)
(August 7, 2006)
Must include with 0203051A.FR8
02052.GR8 (Removal of Buried Man-Made Debris)
(December 6, 2004)
Must include with 02012.GR8 and 0203052.GR8.
10.GR8 GUIDE POSTS
1001.GR8 Description
10011.GR8 (Barrier Delineators)
(April 1, 2002)
Must also use 10021.GR8, 10031.GR8 or
10032.GR8, 10041.GR8, and 10051.GR8.
1002.GR8 Materials
10021.GR8 (Barrier Delineators)
(April 1, 2002)
Must also use 10011.GR8, 10031.GR8 or
10032.GR8, 10041.GR8, and 10051.GR8.
1003.GR8 Construction Requirements
10031.GR8 (Barrier Delineators)
(April 1, 2002)
Delineators placed 6" down from top.
Must also use 10011.GR8, 10021.GR8,
10041.GR8, and 10051.GR8.
10032.GR8 (Barrier Delineators)
(April 1, 2002)
Delineators placed on top of barrier.
Must also use 10011.GR8, 10021.GR8
10041.GR8, and 10051.GR8.
1004.GR8 Measurement
10041.GR8 (Barrier Delineators)
(April 1, 2002)
Must also use 10011.GR8, 10021.GR8
10031.GR8 or 10032.GR8, and 10051.GR8.
1005.GR8 Payment
10051.GR8 (Barrier Delineators)
(April 1, 2002)
Must also use 10011.GR8, 10021.GR8,
10031.GR8 or 10032.GR8, and 10051.GR8.
11.GR8 GUARDRAIL
1101.GR8 Description
1101A.GR8 (Cable Barrier)
(August 5, 2002)
Must also use 1103B.GR8, 1103B.GR8,
11042.GR8, and 11052.GR8.
1101B.GR8 (High-Tension Cable Barrier)
(April 3, 2006)
Must also use 1102B.GR8, 1103C.FR8,
11043.GR8, and 11053.GR8, and 11054.GR8..
1102.GR8 Materials
1102A.GR8 (Cable Barrier)
(April 4, 2005)
Must also use 1101A.GR8, 1103B.GR8,
11042.GR8 and 11052.GR8.
1102B.GR8 (High-Tension Cable Barrier)
(August 6, 2007)
Must also use 1101B.GR8, 1103C.FR8,
11043.GR8, and 11053.GR8, and 11054.GR8.
1103.GR8 Construction Requirements
1103A.GR8 (Box Culvert Guardrail Steel Posts)
(January 5, 1998)
Must also use 11041.GR8 and
11051.GR8.
Use in projects requiring the
construction of steel guardrail
posts on top of existing concrete box
culverts.
1103B.GR8 (Cable Barrier)
(April 4, 2005)
Must also use 1101A.GR8, 1102A.GR8,
11042.GR8, and 11052.GR8.
1103C.FR8 (High-Tension Cable Barrier)
(April 24, 2006)
Must also use 1101B.GR8, 1102B.GR8,
11043.GR8, and 11053.GR8.
Fill-in is the location(s) of Contracting
Agency sites to deliver complete sets of
Additional High-Tension Cable Barrier Components.
(1 fill-in)
1103D.GR8 (Beam Guardrail Type 31 NB)
(August 6, 2007)
Use in projects that contain Type 31 NB Guardrail.
11031.GR8 Beam Guardrail
11031C.GR8 Erection of Rail
(August 6, 2007)
Use in projects requiring snow load washers.
Consult Region Operations for determination
of need.
1104.GR8 Measurement
11041.GR8 (Box Culvert Guardrail Steel Posts)
(March 13, 1995)
Must include with 11031.GR8.
Use in projects requiring the
construction of steel guardrail
posts on top of concrete box
culverts.
11042.GR8 (Cable Barrier)
(April 4, 2005)
Must also use 1101A.GR8, 102A.GR8,
1103B.GR8, and 11052.GR8.
11043.GR8 (High-Tension Cable Cable Barrier)
(April 3, 2006)
Must also use 1101B.GR8, 1102B.GR8,
1103C.FR8, 11053.GR8, and 11054.GR8.
1105.GR8 Payment
11051.GR8 (Box culvert guardrail steel posts)
(September 30, 1996)
Must include with 11031.GR8.
Use in projects requiring the
construction of steel guardrail
posts on top of concrete box
culverts.
11052.GR8 (Cable Barrier)
(April 4, 2005)
Must also use 1101A.GR8, 1102A.GR8,
1103B.GR8, and 11042.GR8.
11053.GR8 (High-Tension Cable Barrier)
(April 2, 2007)
Must also use 1101B.GR8, 1102B.GR8,
1103C.FR8, 11043.GR8, and 11054.GR8.
11054.GR8 (Additional High-Tension Cable Barrier Components)
(April 2, 2007)
Must also use 1101B.GR8, 1102B.GR8, 1103C.FR8,
11043.GR8 and 11053.GR8. No Federal funding participation.
Must be in state funds group.
12.GR8 CHAIN LINK FENCE AND WIRE FENCE
1202.GR8 Materials
12021.FR8 (Coated chain link fence)
(November 27, 1995)
Use in projects requiring the
construction of coated chain link
fence. Must include 12051.GR8.
(1 fill-in)
1205.GR8 Payment
12051.GR8 (Coated chain link fence)
(April 1, 2002)
Use in projects requiring the
construction of coated chain link
fence.
13.GR8 MONUMENT CASES
1301.GR8 Description
13011.GR8 (Monument pipes included in work)
(March 13, 1995)
Must also use 13021.GR8, 13031.GR8,
13041.GR8 and 13051.GR8.
Use in projects requiring that the
monument pipes be installed by the
Contractor.
1302.GR8 Materials
13021.GR8 (Monument pipes included in work)
(March 13, 1995)
Must include with 13011.GR8.
Use in projects requiring that the
monument pipes be installed by the
Contractor.
1303.GR8 Construction Requirements
13031.GR8 (Monument pipes included in work)
(March 13, 1995)
Must include with 13011.GR8.
Use in projects requiring that the
monument pipes be installed by the
Contractor.
1304.GR8 Measurement
13041.GR8 (Monument pipes included in work)
(March 13, 1995)
Must include with 13011.GR8.
Use in projects requiring that the
monument pipes be installed by the
Contractor.
1305.GR8 Payment
13051.GR8 (Monument pipes included in work)
(April 28, 1997)
Must include with 13011.GR8.
Use in projects requiring that the
monument pipes be installed by the
Contractor.
15.GR8 RIPRAP
1504.GR8 Measurement
1504A.GR8 Must use once preceding the
following: 15041.GR8, 15042.GR8,
15043.GR8, and 15045.GR8.
15041.GR8 (Streambed sediment and streambed cobbles by the ton)
(August 6, 2007)
Must include with 15051.GR8.
Use in projects requiring the use of
streambed sediment and streambed cobbles
measured and paid by the ton.
15042.GR8 (Streambed sediment and streambed cobbles
by the cubic yard)
(August 6, 2007)
Must include with 15052.GR8.
Use in projects requiring the use of
streambed sediment and streambed cobbles
measured and paid by the cubic yard.
15043.GR8 (Special excavation)
(March 13, 1995)
Must also use 15053.GR8.
Use in projects requiring excavation
outside the limits of structure
excavation for riprap at bridge piers
located within streams.
15044.GR8 (Excavation for riprap is included in
cost of riprap)
(February 5, 2001)
Must also use 15054.GR8.
Use in projects with small quantities
of riprap or upon recommendation
of the Construction and Materials
Division.
15045.GR8 (Streambed Boulders and Habitat Bouders)
(August 6, 2007)
Must also use 15055.GR8.
Use in projects requiring the use of
streambed boulders and habitat boulders.
1505.GR8 Payment
1505A.GR8 Must use once preceding the
following: 15051.GR8, 15052.GR8,
15053.GR8, and 15055.GR8.
15051.GR8 (Streambed sediment and streambed cobbles
by the ton)
(August 6, 2007)
Mustinclude with 15041.GR8.
Use in projects requiring the use of
streambed sediment and streambed cobbles
measured and paid by the ton.
15052.GR8 (Streambed sediment and streambed cobbles
by the cubic yard)
(August 6, 2007)
Must include with 15042.GR8.
Use in projects requiring the use of
streambed gravel measured and paid
by the cubic yard.
15053.GR8 (Special excavation)
(September 30, 1996)
Must include with 15043.GR8.
Use in projects requiring excavation
outside the limits of structure
excavation for riprap at bridge
piers located within streams.
15054.GR8 (Excavation for riprap is included
in cost of riprap)
(March 13, 1995)
Must include with 15044.GR8.
Use in projects with small quantities
of riprap or upon recommendation
of the Construction and Materials
Division.
15055.GR8 (Streambed Boulders and Habitat Bouders)
(August 6, 2007)
Must also use 15045.GR8.
Use in projects requiring the use of
streambed boulders and habitat boulders.
16.GR8 CONCRETE SLOPE PROTECTION
1603.GR8 Construction Requirements
160302.GR8 Placing Semi-Open Concrete Masonry Units
1603021.GR8 (Requirements for semi-open precast
masonry units)
(December 19, 2005)
Must include with 16051.GR8.
Use in projects requiring semi-open
concrete masonry slope protection.
1605.GR8 Payment
16051.GR8 (Semi-open Conc. Masonry Slope Protection)
(September 30, 1996)
Must include with 1603021.GR8.
Use in projects requiring semi-open
concrete masonry slope protection.
20.GR8 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, AND
ELECTRICAL
2002.GR8 Materials
20022.GR8 Light And Signal Standards
200221.GR8 Light Standards With Type 1 Luminaire
Arms
(August 4, 2008)
Use in projects requiring Type 1
luminaire arms and the Engineer
is not required to verify the H1
distances shown in the Plans.
200222.GR8 Light Standards With Type 1 Luminaire
Arms
(August 4, 2008)
Use in projects requiring Type 1
luminaire arms and H1 distances
are not shown in the Plans or the
Engineer is required to verify
the H1 distances shown in the Plans.
200223.GR8 Light Standards With Type 2 Luminaire
Arms
(August 4, 2008)
Use in projects requiring Type 2
luminaire arms and the Engineer
is not required to verify the H1
distances shown in the Plans.
200224.GR8 Light Standards With Type 2 Luminaire
Arms
(August 4, 2008)
Use in projects requiring Type 2
luminaire arms and H1 distances
are not shown in the Plans or the
Engineer is required to verify
the H1 distances shown in the Plans.
200225.GR8 Traffic Signal Standards
(August 4, 2008)
Use in projects requiring traffic
signal standards, or combination
traffic signal/light standards with
Type 1 luminaire arms, or both.
200226.GR8 Traffic Signal Standards
(August 4, 2008)
Use in projects requiring traffic
signal standards, or combination
traffic signal/light standards with
Type 2 luminaire arms, or both.
200201.GR8 Equipment List And Drawings
2002011.GR8 (Light standards when H1 dimension is
shown on the Plans)
(March 13, 1995)
Use in projects with illumination
systems and the lighting standard
H1 dimension is shown in the Plans
and verification by the Engineer
is not required prior to fabrication.
2002012.GR8 (Light standards when H1 dimension is
not shown on the Plans or must be
verified prior to fabrication.)
(March 13, 1995)
Use in projects with illumination
systems and the lighting standard
H1 dimension is not shown in the
Plans or the dimension shown in the
Plans must be verified by the
Engineer prior to fabrication.
2002013.GR8 (Traffic signal standards, strain pole
standards or combination traffic
signal/lighting standards)
(March 13, 1995)
Use in projects with traffic signal
systems when standards are to be
installed.
2003.GR8 Construction Requirements
200308.GR8 Wiring
20CHART.GR8 Field Wiring Chart
(March 13, 1995)
Use in projects with traffic signal
systems.
200314.GR8 Signal Systems
200314A.GR8 Signal Controllers
200314A1.GR8 Testing
(March 13, 1995)
Use in projects with Contractor
furnished signal controllers.
24.GR8 ROCK AND GRAVITY BLOCK WALL, AND GABION CRIBBING
2402.GR8 Materials
24021.GR8 (Gravity Block Wall)
(January 7, 2002)
Use in projects constructing gravity block
walls. Include with 2403021.GR8.
2403.GR8 Construction Requirements
240302.GR8 Gravity Block Wall
2403021.GR8 (Gravity Block Wall)
(January 7, 2002)
Use in projects constructing gravity block
walls. Include with 24021.GR8.
25.GR8 GLARE SCREEN
(April 1, 2002)
Use in projects when the work zone
analysis determines the need for
temporary barrier screening.
50.GR8 WILDLIFE REFLECTORS
(August 4, 2003)
Use in projects requiring the use
of wildlife reflectors.
53.GR8 FIELD OFFICE BUILDING
5301.GR8 Description
(March 13, 1995)
Use in projects when a field
office building is required.
5303.GR8 Construction Requirements
53031.GR8 (Field office building requirements)
(March 13, 1995)
Use in projects when a field
office building is required.
5305.GR8 Payment
(October 28, 1996)
Use in projects when a field
office building is required.
54.GR8 BOLLARDS
(April 4, 2005)
Use in projects requiring bollards.