Bid opening results
Find results for recent highway, ferry terminal and facility bids including preliminary bid results, verified bid results, subcontractor information and business use.
Disclaimer: preliminary bid results are provided as a convenience to contractors for informational purposes, but should be used for reference only as bids are manually reviewed for mathematical accuracy.
If a change has been made to a contractors bid amount or bid position after review, it will be marked with two asterisks.**
- Preliminary bid total results: (the numbers read publicly directly from submitted bids during bid opening) are posted immediately after the close of bid opening.
- Verified bid total results: mathematically corrected bid numbers along with subcontractors named and Disadvantaged Business Enterprise, Small Business Enterprise and Veteran-Owned Business information.
4/10/2024 bid opening - Olympia, WA
Item no. 1: SR 520, Floating Bridge and Approaches Bridge Decks and Soffit Sealer
Contract number: XE3516
Engineer's estimate: base + A1 + A2 $5,068,305.00
Funds available: $4,800,000.00
Number of addenda: 3
Number of bidders: 4/2
Award status: pending
Preliminary bid total results
Apparent low: base + A1 + A2 - Combined Construction, Inc. - $1,889,945.00
Apparent second: base + A1 + A2 - C. A. Carey Corporation - $4,998,809.00
Verified bid total results
Low bidder: Combined Construction, Inc.
Bid amount base + A1 + A2: $1,889,945.00
Subcontractor named
- Self perform
Description of work: rebar installation, structural steel installation
Small business enterprise (SBE)
- Hughes Group, LLC - sub - $67,000.00
Description of work: traffic control - Caskan, Inc. dba Prime Ops - sub - $28,000.00
Description of work: traffic control - security
SBE goal: $94,497.25
SBE total: $95,000.00
Veteran-owned business (VOB)
- Hughes Group, LLC - sub - $38,000.00
Description of work: traffic control
VOB goal: $37,798.90
VOB total: $38,000.00
Second bidder: C. A. Carey Corporation
Bid amount base + A1 + A2: $4,998,809.00
Subcontractor named
- None proposed
Description of work: none proposed
Small business enterprise (SBE)
- T&T Traffic Control, LLC - sub - $300,000.00
Description of work: traffic control
SBE goal: $249,940.45
SBE total: $300,000.00
Veteran-owned business (VOB)
- C&J Contracting Services - sub - $57,600.00
Description of work: ESC lead - Waterline Construction Services - sub - $60,000.00
Description of work: platform
VOB goal: $99,976.18
VOB total: $117,600.00
4/3/2024 bid opening - Olympia, WA
Item no. 1: NSC Spokane River to Columbia Phase 2
Contract number: XE3523
Engineer's estimate: $3,458,504.10
Number of addenda: 3
Number of bidders: 2/2
Award status: awarded 4/17/2024
Preliminary bid total results
Apparent low: Acme Concrete Paving, Inc. - $3,525,000.00
Apparent second: Cameron-Reilly, LLC - $3,702,299.00
Verified bid total results
Low bidder: Acme Concrete Paving, Inc.
Bid amount: $3,525,000.00
Subcontractor named
- Midland Electric
Description of work: item 43, sign bridge no. 1, item 44, ITS no.1 revisions
Small business enterprise (SBE)
- Spokane Traffic Control - sub - $200,000.00
Description of work: temp traffic control (labor)
SBE goal: $176,250.00
SBE total: $200,000.00
Veteran-owned business (VOB)
- Acme Concrete Paving, Inc. - prime - $1,000,000.00
Description of work: cement concrete paving
VOB goal: $70,500.00
VOB total: $1,000,000.00
Second bidder: Cameron-Reilly, LLC
Bid amount: $3,702,299.00
Subcontractor named
- Versatile
Description of work: rebar installation - Power City Electric
Description of work: electrical - Power City Electric
Description of work: structural steel installation
Small business enterprise (SBE)
- North Star Enterprises - sub - $77,000.00
Description of work: traffic control services - North Star Enterprises - sub - $3,680.00
Description of work: joint adhesive - North Star Enterprises - sub - $2,300.00
Description of work: erosion control - Rhodes Crane & Rigging - sub - $14,000.00
Description of work: craning services - Versatile Drilling Contract - sub - $92,300.00
Description of work: drilled shafts
SBE goal: $185,114.95
SBE total: $189,280.00
Veteran-owned business (VOB)
- Thompson Metal Fab - manufacturer/supplier - $95,000.00
Description of work: sign bridge manufacturer
VOB goal: $74,045.98
VOB total: $95,000.00
Item no. 2: 2024 CW Branch SR 904 Betz Rd Crossing - PCC
Contract number: XE3525
Engineer's estimate: $2,238,207.69
Number of addenda: 1
Number of bidders: 2/2
Award status: pending
Preliminary bid total results
Apparent low: Railworks Track Systems, LLC - $2,124,994.00
Apparent second: Halme Construction, Inc. - $3,498,422.70
Verified bid total results
Low bidder: Railworks Track Systems, LLC
Bid amount: $2,124,994.00
Subcontractor named
- None proposed
Description of work: none proposed
Small business enterprise (SBE)
- Combat Action Construction, LLC - sub - $16,410.00
Description of work: partial - Combat Action Construction, LLC - sub - $29,430.00
Description of work: demo - Combat Action Construction, LLC - sub - $14,715.00
Description of work: demo - Combat Action Construction, LLC - sub - $14,715.00
Description of work: demo - Combat Action Construction, LLC - sub - $5,000.00
Description of work: excavate/haul - Combat Action Construction, LLC - sub - $15,000.00
Description of work: partial - install - Combat Action Construction, LLC - sub - $17,576.25
Description of work: partial - prep/grade - Combat Action Construction, LLC - sub - $17,576.25
Description of work: partial - prep/grade - Combat Action Construction, LLC - sub - $17,576.25
Description of work: partial - prep/grade - Combat Action Construction, LLC - sub - $17,576.25
Description of work: partial - prep/grade - Spokane Traffic Control - sub - $1,850.00
Description of work: partial - Spokane Traffic Control - sub - $4,000.00
Description of work: repair - Spokane Traffic Control - sub - $23,500.00
Description of work: traffic control - Spokane Traffic Control - sub - $27,748.00
Description of work: construct - O'Bunco Engineering International, Inc. - sub - $9,335.00
Description of work: survey
SBE goal: $106,249.70
SBE total: $232,008.00
Veteran-owned business (VOB)
- Wm. Winkler, Co. - sub - $3,500.00
Description of work: partial - Wm. Winkler, Co. - sub - $2,068.98
Description of work: partial construct - Wm. Winkler, Co. - sub - $2,474.31
Description of work: partial construct - Wm. Winkler, Co. - sub - $3,519.83
Description of work: partial construct - Wm. Winkler, Co. - sub - $1,457.28
Description of work: construct - Wm. Winkler, Co. - sub - $1,489.87
Description of work: survey - Columbia Basin Striping, LLC - sub - $6,000.00
Description of work: partial - Columbia Basin Striping, LLC - sub - $1,175.00
Description of work: demo - Columbia Basin Striping, LLC - sub - $13,200.00
Description of work: demo - Columbia Basin Striping, LLC - sub - $4,400.00
Description of work: demo - Columbia Basin Striping, LLC - sub - $6,555.00
Description of work: construct - Columbia Basin Striping, LLC - sub - $4,400.00
Description of work: construct - Columbia Basin Striping, LLC - sub - $1,880.00
Description of work: construct - Columbia Basin Striping, LLC - sub - $9,600.00
Description of work: construct - Columbia Basin Striping, LLC - sub - $7,200.00
Description of work: construct - Columbia Basin Striping, LLC - sub - $2,880.00
Description of work: construct
VOB goal: $42,499.88
VOB total: $71,800.27
Second bidder: Halme Construction, Inc.
Bid amount: $3,498,422.70
Subcontractor named
- None proposed
Description of work: none proposed
Small business enterprise (SBE)
- Obunco Engineering - sub - $14,540.00
Description of work: surveying - North Star Enterprises - sub - $94,000.00
Description of work: traffic control - All Power Trucking & Construction - sub - $66,500.00
Description of work: trucking
SBE goal: $174,921.14
SBE total: $175,040.00
Veteran-owned business (VOB)
- WM. Winkler - sub - $14,510.00
Description of work: concrete work - Columbia Basin Striping - sub - $57,290.00
Description of work: striping
VOB goal: $69,968.45
VOB total: $71,800.00
Slow down – lives are on the line.
In 2023, speeding continued to be a top reason for work zone crashes.
Even one life lost is too many.
Fatal work zone crashes doubled in 2023 - Washington had 10 fatal work zone crashes on state roads.
It's in EVERYONE’S best interest.
95% of people hurt in work zones are drivers, their passengers or passing pedestrians, not just our road crews.